Coleraine Drive grade separation
Environmental assessment for South of Old Ellwood Drive
Notice of study completion
August 8, 2024 – The Region of Peel has completed a Municipal Class Environmental Assessment (EA) Study for a grade separation of the Canadian Pacific Railway (CP) on Coleraine Drive in the Town of Caledon (see map). The purpose of the study was to consider grade separation improvements of the CP Rail line on Coleraine Drive, south of Old Ellwood Drive. The Study was conducted in compliance with Schedule ‘C’ of the Municipal Class Environmental Assessment (Municipal Engineers Association, as amended in 2015), which is approved under the Ontario Environmental Assessment Act. The recommended improvements include a ‘road-over-rail’ grade separation of Coleraine Drive and the CP Rail Line, and a roundabout at the Coleraine Drive and King Street West / Harvest Moon Drive intersection.
Environmental Study Report (ESR) Review Period
The ESR documents the planning, consultation, preliminary design, and decision-making process undertaken for the project and will be available for review for 42 calendar days starting August 15th, 2024, and ending on September 26th, 2024.
If you have questions or require the notice documents, please contact the project manager.
Tareq Mahmood
Project Manager, Infrastructure Programming & Studies
Region of Peel
10 Peel Centre Drive, Suite B, 4th Floor
Brampton, ON L6T 4B9
Tel: 905-791-7800 ext. 7828
Stephen Keen, P. Eng
Consultant Project Manager
CIMA Canada Inc.
3027 Harvester Road
Burlington ON L7N 3G7
- Environmental Study Report
- Appendix A – Consultation Record
- Appendix B – Transportation Report
- Appendix C – Cultural Heritage Assessment Report
- Appendix D – Stage 1 Archaeological Assessment Report
- Appendix E – Natural Heritage Evaluation Report
- Appendix F – Tree Inventory and Assessment Report
- Appendix G – Drainage and Stormwater Management Report
- Appendix H – Fluvial Geomorphic Assessment Technical Memorandum
- Appendix I – Phase 1 Environmental Site Assessment Report
- Appendix J1 - Design Alternatives - Road Over Rail Option
- Appendix J2 - Design Alternatives - Road Over Rail Option
- Appendix K – Ellwood Dr. and Grapevine Rd. Technical Memorandum
- Appendix L – Indigenous Community Engagement Record
- Appendix M – Preliminary Preferred Design Plates
- Appendix N – Structural Engineering Technical Memorandum
- Appendix O – Geotechnical and Pavement Investigation Report
- Appendix P – Utility Conflict Plan
- Appendix Q – Preliminary Cost Estimate
- Appendix R – Noise Impact Study
- Appendix R1 – Peel Region Private Noise Wall Conversion Policy
- Appendix R2 – Private Noise Wall Locations
- Appendix S – Vibration Assessment Study
- Appendix T – Shadow Impact Study
- Appendix U – Air Quality Report
- Appendix V – Hydrogeological Report
The first PIC was held on October 8, 2019 at the Albion Bolton Community Centre from 6:00 – 8:00 p.m. The review included information on alternative planning solutions, existing conditions, evaluation criteria, and the preliminary preferred solution. The public was also able to ask questions or discuss comments with the project team.
A second PIC took place from December 16, 2021 to January 21, 2022.
Main presentation
Technical and environmental assessments presentation
Supporting documents
- Presentation file
- Presentation transcript
- Technical and environmental assessments presentation file
- Technical and environmental assessments presentation transcript
- Evaluation criteria and assessment
- Preferred preliminary design
Alternative designs
Two alternative design concepts were investigated.
Technical studies
Use the comment sheet to provide feedback to Tareq Mahmood, Region of Peel project manager or Stephen Keen, consultant project manager.
The Project Team will review and consider the feedback received at the PIC and confirm the recommended preliminary design. The next steps of the study include the preparation of an Environmental Study Report (ESR) to document the planning, consultation, and design process. At the end of the study, the ESR will be made available for public review for a minimum of 30 calendar days and at that time, a Notice of Completion will also be issued.
Please provide written comments to Region of Peel Project Manager no later than September 26th, 2024.
Tareq Mahmood, Project Manager, Region of Peel
10 Peel Centre Drive, Suite B, 4th Floor,
Brampton, ON L6T 4B9
In addition, a request may also be made to the Minister of the Environment, Conservation and Parks to make an order for a higher level of study (requiring an individual/comprehensive EA approval before proceeding), or that conditions be imposed (such as the requirement of further studies) on the grounds that the requested Order may prevent, mitigate, or remedy adverse impacts on constitutionally protected Aboriginal and treaty rights. Requests should be sent in writing or by email by 4:30 p.m. on Thursday, September 26th, 2024, to the address provided below and include the requester’s contact information and full name of the Ministry.
Ministry of Environment, Conservation and Parks
777 Bay Street, 5th Floor
Toronto ON M7A 2J3
E-mail: minister.mecp@ontario.ca
Ministry of Environment, Conservation and Parks
135 St. Clair Ave. W, 1st Floor
Toronto ON, M4V 1P5
E-mail: EABDirector@ontario.ca
A copy of the order request must also be sent to the Peel Region Project Manager by mail or email.
The Region of Peel is committed to ensure that all regional services, programs, and facilities are inclusive and accessible for persons with disabilities. Please contact the Project Manager if you need any disability accommodation to review the study documents.