Port Credit East Water and Wastewater Servicing Optimization Strategy

Schedule “C” Municipal Class Environmental Assessment

Background

The existing sewage pumping stations (Rosemere, Elmwood, and Hiawatha) and some of the sewage sewer mains and watermains in the general Port Credit East area are experiencing operational challenges. The Region has completed a Schedule “C” Municipal Class Environmental Assessment (EA) for this infrastructureand has selected a preferred integrated and optimized servicing strategy to meet existing and future growth.

Environmental Study Report (ESR)

The ESR is available for an extended 30-day public review period starting November 16, 2023 and ending January 4, 2024, in accordance with the requirements of the Municipal Class EA process.

Contact information

To be added to the mailing list or to receive further information about the project, please contact:

Italia Ponce, P.Eng. Project Manager Region of Peel 905-791-7800, ext. 4583

Study commencement - November 5, 2020

PIC #1 – August 25, 2021

PIC #2 – May 18, 2022

PIC #3 – June 14, 2023