Project 21-1951
Snelgrove Elevated Tank decommissioning update
This project is for construction work to demolish the Snelgrove Elevated Water Tank located just south of Mayfield Road off Cresthaven Road.
Background
The Elevated Tank was expected to be taken out of service before 2020 once the Victoria Reservoir and feedermain were constructed. However, when the reservoir work was deferred, the tank decommissioning was also deferred, and over time the Snelgrove Elevated Tank appearance worsened.
Project update
Tank decommissioning timeline
- Telecommunications infrastructure removed from tank - Summer 2022 - completed
- Upgrades within existing watermain system - Fall 2022 - completed
- Engage an engineering consulting firm - Winter 2023 - completed
- Active construction starts – Spring 2025
- Active construction is completed – Fall 2025
Should you have any questions about the project, please contact:
Water Facilities Engineering and Reliability
Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409