Project 12-4085
Reconstruction of the Gore Road from Patterson Side Road to 100m North Finnerty Sideroad - Town of Caledon - Gore Road Reconstruction
Project updates
- August 26 – September 11, 2024: Extended closure of The Gore Road
- August 26 – September 6, 2024: The Gore Road Closure
- November 15, 2023: Hot mix asphalt placement
Where the work is happening
On The Gore Road between Patterson Side Road to Finnerty Sideroad
What we are doing
The work includes:
- Clearing, grubbing, earthworks excavation;
- New granular road base asphalt pavement;
- Culvert replacements;
- Precast modular retaining walls;
- Intersection lighting;
- Landscaping.
When
Construction Start: September 2023 to Finish: Summer 2025, (weather permitting)
Working Hours
Pacific Paving Limited has been contracted to complete the work on the Region’s behalf. Hours of operation are from 7:00 a.m. to 5:30 p.m., Monday to Friday.
Traffic Control
A lane per direction is to be maintained whenever possible. Should a lane per direction not be possible, the Contractor’s work shall allow a minimum of a single lane of traffic and shall have a flag person and / or temporary signals onsite at all times to guide traffic.
Emergency access will be maintained at all times.
Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.
Driveway Access
When working on driveways, the Contractor will stage their work to maintain, at minimum one half of the entrance for vehicular and pedestrian traffic.
Project updates
The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
We are committed to ensuring minimum disruption to your homes.
Please call the project manager if you have any special needs.
Contact
Randy Chawb-Naraine
Project Manager
Region of Peel
905-791-7800 ext. 7962