Project 19-4517 - Steeles Avenue
Steeles Avenue noise wall replacement
Streets affected: Steeles Avenue from Hartford Trail to McMurchy Avenue South.
We have finished the work. The project is under warranty until December 2025.
Construction is planning to start in July 2022 and be completed in Spring 2023 (weather permitting).
The work includes:
- Clearing and grubbing;
- Removal and disposal of existing wall and/or fence;
- Installing temporary fence;
- Installation of new noise attenuation wall;
- Extension of existing backyard fences to new noise attenuation wall;
- Restoration; and minor related works.
Working hours
Injaz Construction Limited has been contracted to complete the work on the Region’s behalf. Their hours of operation are from 8 a.m. to 6 p.m., Monday to Friday. These hours follow the city’s by-laws.
Traffic control
- Temporary lane closures will be required during non-peak hours.
- Emergency access will be maintained at all times.
- Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.
Driveway access
We anticipate no impact to any driveway access.
Project updates
- The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
- We are committed to ensuring minimum disruption to your homes.
- Please call the project manager if you have any special needs.
Sujan Kisiju
Project Manager, Region of Peel
10 Peel Centre Drive, Suite B, 4th Floor
Brampton, ON L6T 4B9
Tel: 905-791-7800 ext. 7813
Toll Free: 1-888-919-7800