Project 10-4040
Streets affected: Bovaird Drive to Wanless Drive
Project updates
- Mississauga Road driveway access interruptions (November 20 to November
27, 2024). - Sandalwood Parkway driveway closure (September 30 to October 4, 2024)
- Mississauga Road driveway closure (September 30 to October 4, 2024)
- Sandalwood Parkway driveway closure (September 16 to September 20, 2024)
- Access Restrictions to and from Mississauga Rd at Muscovy Drive and Fann Drive (August 12 to August 16, 2024)
- Notice of access restrictions (July 29 to August 2,2024)
- Notice of road closure and detour (June 17 to June 21, 2024)
Peel Region is widening and improving Mississauga Road as shown on the attached map. The work includes:
- new road-over-rail bridge separating Mississauga Road from the CN Rail tracks;
- reconstruction and widening of the roadway:
- 2-to-6 lanes from Bovaird Drive to Sandalwood Parkway,
- 2-to-4 lanes from Sandalwood Parkway to Wanless Drive;
- new multi-use pathway along the east side of Mississauga Road;
- new streetlighting, landscaping and boulevard improvements; and,
- traffic intersection and signal improvements.
Construction schedule
We expect to start work in Summer 2023 and finish in Summer 2026.
Typical hours of operation are from 7 a.m. to 7 p.m., Monday to Friday. Some weekend and overnight work is required at the railway bridge to mitigate impact to critical CN Rail and Metrolinx service. Extended working hours may cause some inconvenience however they will help facilitate completion of the project as quickly and safely as possible.
Traffic impacts
- One lane of traffic in either direction will be maintained for most works.
- Single lane reductions will only take place with short duration during off-peak traffic hours for select activities.
- Two separate weekend road closures are required to construct the new road-over-rail bridge.
- Roadside message boards will be posted in advance to notify the travelling public of the upcoming road closures.
- A Mississauga Road closure and traffic detour from Sandalwood Parkway to Bovaird Drive for concurrent TC Energy pipeline works will take place this summer 2023 for two months (July 3 through August 28).
- Access for emergency vehicles and businesses will be always maintained.
- Please use caution when travelling through the work zone and obey all traffic signs, flag persons, and Paid Duty Police Officers when present.
Other impacts
You may feel slight vibrations from the construction work.
Project updates
- Peel Region will always let you know if there are any major changes to the plans while doing our best to minimize disturbing you.
- Construction project updates can also be found at peelregion.ca/construction
Contact
Peel Region
Scott Durdle
Project Manager
905-791-7800, ext. 5052
Asad Rauf
Construction Inspector
905-791-7800, ext. 3246
Dufferin Construction Company
Dufferin Construction Company will do the work, under contract to Peel Region.
Paul Manzo
Senior Site Superintendent
416-984-1222
Milton Tatchell
General Foreman
416-659-1930
RV Anderson Associate Limited
RV Anderson will manage and oversee the work, under contract to Peel Region.
Derek Gretka
Contract Administrator
416-704-3225
Golam Hossain
Construction Inspector
416-399-8178