Project 23-130 D – April 13, 2026 update
Streets affected: Boismere Court
Project update
Peel Region has been replacing the watermain along Boismere Court. This work is required to keep providing you with high-quality water.
At this time, we have:
- Replaced the watermain on street.
- Connected properties to the new watermain on streets.
- Temporarily repaired driveways, road, curbs, sidewalk and sod (grass) affected by construction.
Schedule for remaining restoration work
Construction was paused due to freezing temperatures. We expect to start again on April 10, 2026 to complete the following:
- Complete the repair of driveways, road, curbs, sidewalk and sod (grass) where affected by our construction.
We plan to finish in middle of 2026. These dates may change due to weather and other unexpected events. All work is warrantied for 2 years from the completion date.
Visit the project webpage for more project information and updates on:
- driveway access and repairs
- dust
- in-ground sprinkler systems
- noise
- potential vibrations
- restoring property
- tree trimming
- water interruptions
Get the latest project updates
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide safe drinking water to support a thriving community for life.
If you have any questions, contact us.
Water Linear Engineering
Engineering Services Division
Public Works, Peel Region
Phone: 905-791-7800 ext. 4409