Project 23-1310 D
Streets affected: Boismere Court, Corsair Road, Kalligan Court, Maplewood Road, Proverbs Drive, King Forrest Drive, Shawanaga Trail and Abbotswood Court
Peel Region will be working in your area to replace the watermains along Boismere Court, Corsair Road, Kalligan Court, Maplewood Road, Proverbs Drive, King Forrest Drive, Shawanaga Trail, Abbotswood Court, as shown on the attached maps.
Watermains are underground pipes that bring tap water from our water treatment facility to your neighbourhood. As pipes age and our population grows, we need to replace older watermains to keep providing you with high quality water.
Construction schedule
Construction is planned to begin October 7, 2024, and be completed by the end of July, 2025. These timelines are estimates, as weather and other unexpected events may impact our timelines.
This construction work will be completed one street at a time and will begin on Proverbs Drive and Kalligan Court the week of October 7, 2024. The work will then move onto the other streets and be announced on a later date.
Once the underground work is completed on all streets, we will begin repairing any driveways, boulevards, sod (grass), roads, curbs, and sidewalks impacted by our construction work.
We expect construction on all streets including the associated repair work, to be completed by the end of July 2025. These timelines are estimates, as weather and other unexpected events may impact our timelines.
All work is under warranty for two years from the completion date.
Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices.
What to expect during construction
Learn what to expect during watermain construction by watching our short video. The video goes behind the scenes to show what happens before, during and after construction. This website also answers common questions about:
- Why your water may be temporarily shut off,
- How traffic, parking, and waste collection may be affected,
- How driveways, roads and sod (grass) are repaired after construction is finished.
Contractor and working hours
The work will be completed by Sam Rabito Construction Ltd., under contract to Peel Region. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighbourhood/area to be under construction for a longer period of time.
The City of Mississauga, under the Noise Bylaw, is allowing work to take place on specific date and time or over the weekend or overnight to reduce the impact of our work on traffic congestion.
This overnight or weekend work will occur only after issuing an exemption by the City of Mississauga, and it will be communicated to residents in the affected areas. We apologize in advance for any inconvenience caused by this work.
Traffic and parking
>We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.
Interrupting your water supply
We anticipate that this construction project will require temporarily shutting off your water.
For residents:
- It is our goal to let you know 48 hours (2 days) in advance if we plan to shut off your water for an extended period (several hours). Occasionally we may have to reduce this notice to 24 hours.
- If we need to shut off your water for a short duration (less than one hour), we will knock on your door to notify you.
- If we must shut off your water due to an emergency, we will knock on your door to alert you, and do everything we can to fix the problem as quickly as possible.
For businesses:
- If a continuous water supply is required for your business and you have not already completed a water needs survey, please contact us to let us know when and how your business uses water.
- If we must shut off your water due to an emergency, we will knock on your door to alert you, and do everything we can to fix the problem as quickly as possible.
Areas impacted by construction
Installing watermains usually requires digging a trench within the municipal right-of-way, which includes the street and the land owned by the municipality between the water service box and the street. (The water service box is a small, round, metal valve located outside on the property line between your homes and the road.) Depending on the location of the watermain, this trench might cause temporary damage to roads, curbs, sidewalks, boulevards, lawns, and the bottom of driveways within the municipal right-of-way.
To maintain your water supply, Peel Region will also replace:
- Your water service box,
- The section of your water service pipe leading from the watermain to your water service box. The water service pipe carries water from the watermain to your home.
This requires digging up your water service box located in the lawn or driveway and disturbing an area at least two square meters.
We therefore recommend that you delay any driveway paving or major landscaping projects until this construction work is completed.
Any damage caused by Peel Region’s construction will be repaired.
In-ground sprinkler systems
As the front lawn may be affected by this construction work, if you have an in-ground sprinkler system we strongly recommend moving any sprinkler lines that are located in the municipal right-of-way or next to the sidewalk. If you can’t relocate these sprinkler lines, please send us a map created by your irrigation contractor or flag each sprinkler head that is located within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.
Tree protection and trimming
Trees located in the municipal right-of-way will be protected during construction using temporary fencing. If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand.
If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. The contractor will contact you before any pruning of private trees occurs. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.
Repairing areas impacted by construction
We will start repairing the road, curb, sidewalk, driveways, and lawns once the new watermain is buried and new water service pipes have been connected to all properties on your street.
Repairs may be delayed due to contractor availability or certain seasonal weather conditions.
For example:
- Paving cannot take place when the ground is saturated with water, or the temperature is below 3°C.
- Asphalt is not available in large volumes during the winter. Asphalt usually becomes available around mid-May.
- Most sod farms are located north of Peel. They usually have sod available beginning in late May. We will replace the sod on your property once it is available. We replace sod only until the middle of November, weather permitting, to let the sod grow roots. If we do not repair your lawn by the middle of November, we’ll replace the sod the following spring.
Repairing grassy areas
The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.
Repairing driveways
- Asphalt driveways: If we need to cut a section of your driveway, the driveway will be repaired by paving a stripe over the disturbed area, resulting in minimal seams in the final driveway. Peel Region cannot replace your entire driveway. If you would like to have the rest of your driveway paved, please contact the contractor, Sam Rabito Construction Ltd, at (905) 642-5356. The contractor will then share contact information for the company hired to do the paving repairs. Please remember this is your option. If you decide to have your entire driveway repaved, this extra paving work is your responsibility and outside the jurisdiction of Peel Region.
- Interlock or concrete driveways: If we damaged a portion of your driveway, our contractor will reinstate the damaged portion of the driveway.
Temporary restoration
On the following Streets: Shawanaga Trail, and Abbotswood Court and Maplewood Road, The City of Mississauga is planning to complete roadwork on your street within the next few years. As this roadwork may also impact driveways, curbs, sidewalks, and lawns next to the sidewalk, we will:
- Pave only the areas of the street directly disturbed,
- Fix damaged sidewalks and curbs using asphalt,
- Patch your driveway to cover any places we disturbed, as the future roadwork may affect the bottom of your driveway. After the city/town paves your street, the driveway will be repaired by paving a stripe over the disturbed area, resulting in minimal seams in the final driveway.
Peel Region’s repairs are temporary, as the City of Mississauga will complete restoration as part of their roadwork. The City of Mississauga will send you a separate notice about this additional construction.
Driveway access
It may be necessary to block your driveway for a short time when crews are digging the trench for the watermain, replacing your water service box and pipe, or completing other construction activities. Please contact us if you have special needs related to access.
Waste collection
If you receive waste collection from Peel Region, your garbage, recycling, and organics will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin. This helps us return empty bins to the correct address.
Vibrations
You could feel slight vibrations from the construction work.
Optional protection plans for your exterior water pipes, wastewater pipes, and in-home plumbing
Many homeowners are not aware that they are responsible for maintaining the water and wastewater pipes both inside their home and outdoors up to the property line. If one of these pipes breaks, it can cause unexpected and costly repairs. Peel Region has partnered with Service Line Warranties of Canada (SLWC) to offer homeowners optional, affordable protection from unexpected home repairs. Learn more about the protection plans at plansforpeel.ca.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones.
Keeping you informed
We will let you know if there are any major changes to the plans.
Follow Peel Public Works on Twitter for project updates.
We value your feedback
After we have finished, we will invite you to provide feedback on the construction project.
You can sign up to receive this survey electronically.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions, please contact us.
Water Linear Engineering
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409