Project 19-2215/19-1120 - November 11, 2021 update
Pre-design field investigation
Streets affected: Lakeshore Corridor from Jack Darling Park to Elmwood Avenue and Pine Avenue S.
What are we doing
- Performing field investigation services along the Lakeshore Road corridor between Elmwood Avenue and Jack Darling Park.
- Work involves utility stakeouts, boreholes, surveying and photographing assets in the project area as well as test pits to confirm utility locations.
Why
- To determine soil conditions and verify the location of existing underground and above ground utilities along the Lakeshore corridor for design and construction of future Regional infrastructure.
When
- We expect to start work on or about December 14, 2020.
- The project should be completed by December 31, 2021.
What to expect
- Minor traffic disruptions.
- Working hours are Monday to Friday from 7am to 7pm.
- There may be occasional Saturday work from 9:00 a.m. to 5:00 p.m.
Project updates
- The Region encourages you to notify the Region of Peel Project Manager if you have special requirements, or if you have any comments or concerns.