Project 18-1169 – Nov 11, 2024 update
Streets affected: Goreway Drive/Humberwest Parkway at Queen Street East
Peel Region has been working in your neighbourhood to install watermains and sanitary sewer pipes along Queen Street East. This work is required to maintain and improve existing water and wastewater services.
At this stage in the project, temporary lane reductions will be required as follows:
- Humberwest Parkway as noted below will be extended to December 31st, 2024.
- Goreway Drive as noted between November 13th and December 31st, 2024.
Traffic impacts – Humberwest Parkway north of Queen Street East:
- Northbound Humberwest Parkway will be reduced to two lanes from Queen Street East to just south of Goreway Drive.
- The multi-use path / sidewalk in this area will remain open with partial diversion to the curb lane.
- The Brampton Transit bus stops in this area will remain unaffected, including:
- Humberwest Parkway Route 5: Stop ID 2486.
- Two lanes of traffic in each direction will always remain open, unless notified otherwise.
- Digital road signs will remain in place throughout the work and will be updated accordingly.
Traffic Impacts – Goreway Drive south of Queen Street East:
- Between 7am and 3pm Northbound Goreway Drive will be reduced to one lane between Auction Lane and Queen St.
- Between 3pm and 7am Northbound Goreway Drive will be reduced to two lanes between Auction Lane and Queen St.
- An alternative detour route (Westbound Auction Lane) for the traffic from Northbound Goreway Drive to Westbound Queen St East will be clearly marked with road signs
- The multi-use path / sidewalk on the east side of Goreway Dr. will be closed in this area.
- Goreway Drive Route 5: Stop ID 2485 will be temporarily closed.
- All driveway access will be maintained.
- One southbound left through lane will occasionally be closed.
- Digital road signs will remain in place throughout the work and will be updated accordingly.
We apologize for any delays or inconvenience resulting from these traffic impacts.
Keeping you informed
Weather and other unpredictable events may change the date of these traffic impacts. Receive timely project updates right to your inbox by signing up for e-notices.
Follow Peel Public Works on Twitter for project updates.
Information on this construction project can also be found on the project page.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water and wastewater services. If you have any questions, please contact us.
Water Linear Engineering & Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409