Project 16-1177 - November 8, 2022 update
Streets affected: Mayfield Road from Martin Byrne Drive to Coleraine Drive and The Gore Road from Mayfield Road to 250m North of Squire Ellis Drive.
The Region of Peel will be repairing driveways, roads, curbs, sidewalks, and sod (grass) following the installation of the new watermain on Mayfield Road and The Gore Road.
Restoration schedule
This restoration work has begun in some locations and will continue up to mid-December. We plan to complete all restoration work by mid-December 2022, weather permitting. Depending on the weather, sod may be placed in April or May 2023 when it becomes available.
Restoration work will begin by fixing curbs. This will be followed by driveway and road paving repairs. Sod will then be replaced where grass has been damaged. Seeding will be placed in all other areas where field grass has been disturbed. This process will take approximately six weeks if weather conditions are favorable.
As restoration work progresses, we may provide more detailed timelines through email. Receive these timely updates by signing up for e-notices.
Please note that repairs may be delayed due to contractor availability or weather conditions.
For example:
- Paving cannot take place when the ground is saturated with water, or the temperature is below 3°C.
- Asphalt is not available in large volumes during the winter. Asphalt usually becomes available around mid-May.
- Most sod farms are located north of Peel. They usually have sod available beginning in late May. We will replace the sod on your property once it is available.
- In summer we may need to postpone sod replacement due to hot, dry weather. We will lay the sod once weather permits.
- We replace sod only until the middle of November, weather permitting, to let the sod grow roots. If we do not repair your lawn by the middle of November, we’ll replace the sod the following spring.
Contractor and working hours
The work will be overseen by Pacific Paving Limited under contract to the Region of Peel. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your area to be under construction for a longer period.
Traffic
We may need to reduce traffic to a single lane or implement lane shifts during construction. If we must reroute traffic, we will place signs giving directions.
In-ground sprinkler systems
If the area in front of your home or business was affected by the construction work, in-ground sprinkler lines may be impacted during the upcoming repairs to sod, driveways, sidewalks and curbs. We strongly recommend moving any sprinkler lines that are located next to the sidewalk or driveway, or within the municipally owned right-of-way. The right-of-way is the land owned by the municipality between the street and your water service box (small, round metal valve in either your driveway or lawn).
If you can’t relocate these sprinkler lines, please:
- Send us a map created by your irrigation contractor, or
- Flag each sprinkler head that is located near the sidewalk, curb, and driveway (if you have not done so already).
This will allow us to minimize the impact to your sprinkler system.
Replacing and taking care of your sod
The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in rather than evaporating.
Driveway repairs
Asphalt driveways: If we have cut your driveway, the driveway will be repaired by paving a strip over the disturbed area, resulting in minimal seams in the final driveway. The Region of Peel cannot replace your entire driveway.
If you would like to have the rest of your driveway paved, please contact the contractor, Pacific Paving Limited, at 905-670-7730. The contractor will then share contact information for the company hired to do the paving repairs. Please remember this is your option. If you decide to have your entire driveway repaved, this extra paving work is your responsibility and outside the jurisdiction of the Region of Peel.
Interlock or concrete driveways: If we damaged a portion of your driveway, our contractor will reinstate the damaged portion of the driveway.
Temporary restoration
The Region of Peel is planning to complete roadwork on your street within the next few years. As this roadwork may impact the driveway, boulevard, street, curbs, and sidewalks, we will:
- Pave only the areas of the street directly disturbed,
- Fix damaged sidewalks and curbs with concrete,
- Patch your driveway to cover any places we disturbed, as the future roadwork may affect the bottom of your driveway.
The Region of Peel’s repairs are temporary, as the Region will complete restoration as part of their roadwork. The Region will send you a separate notice about this additional construction.
Driveway access and parking
We may need to block your driveway for a short time during paving activities. Whenever possible, we will work to ensure businesses can be accessed.
Please avoid parking in your driveway when it is being repaired to provide maximum access to the construction crew. The construction crew will knock on your door before work on your driveway begins. If you will not be home weekdays between 7 a.m. and 7 p.m. during driveway paving, please do not leave any vehicles in the driveway.
Once the driveway is repaired, it is important to avoid driving on the new asphalt for the first three hours afterwards, and to avoid parking on the new asphalt for one day.
Please email us if you have special needs related to driveway access.
Road repairs
We will repair the road where it was disturbed by our recent watermain construction. Road repairs have begun and we expect these paving activities to be completed by end of November, weather permitting.
Warranty on construction repairs
Repair work completed as part of this watermain project is under warranty for two years from the completion date.
It is normal for repaired areas to settle a bit in the coming months. If you notice large potholes forming where the driveway, street, or lawn was repaired, please let us know and we will ensure the contractor fixes this before the end of the warranty period.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn how to stay safe in construction zones.
Staying informed
Information on this construction project can also be found on the project homepage.
We will let you know if there are any major changes to the plans.
Thank you for your patience as we complete this restoration work. If you have any questions or concerns, please contact us.
Water Linear Engineering and Reliability
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409