Project 16-1177 - July 6, 2021 update
Streets affected: The Gore Road at Mayfield Road.
We wish to thank you for your patience and courtesy while our construction takes place along Mayfield Road. Watermain installation is proceeding east from The Gore Road along Mayfield Road towards Coleraine Drive over the next several months.
This project notice is to inform you that The Gore Road will be closed to all traffic at a localized location just north of Mayfield Road. During this time, a detour route will be in place to assist traffic approaching or using The Gore Road. We ask that during this time, please drive carefully and obey the detour signs and temporary posted speed limits. There may be some minor delays at certain times, at the intersection of Mayfield Road and The Gore Road, so we ask for your patience. We will try to keep the delays to a minimum.
What are we doing
Removing unsuitable soils found during the watermain installation, at the northeast corner of The Gore Road and Mayfield Road intersection.
Why
Unsuitable soils will be replaced with suitable soils to accommodate the construction of the future road widening on Mayfield Road.
When
The road closure is expected to occur on July 12, 2021 for approximately 2 weeks (weather dependent).
Contact
Region of Peel
Melvin Gonzalez Project Manager
289-541-5777
Joseph Vivilecchia
Regional Construction Inspector
437-995-3620
GMBP Consultants
Zoltan Tako
Contract Administrator
519-501-4161
Eric McLennan
Lead Construction Inspector
226-821-4064
Pacific Paving Limited
Pacific Paving Limited will do the work, under contract to the Region of Peel
Dino Marchioni
Project Lead
905-670-7730
Danny Jennings
General Site Superintendent
416-318-9015
What does this mean for you
Vehicles will be diverted around the closed section, as per the attached map.
Access to all homes and businesses on The Gore Road will be available from Healey Road.