Project 16-1177 - February 23, 2022 update
Streets affected: 8373 and 8387 Mayfield Road.
Work to be done
As part of the watermain construction on Mayfield Road, trees and fencing located in front of your property will be removed within the Region’s widened right-of-way and disposed of, as per the attached sketch.
If you wish to keep any of the fencing materials, gates, and light standards for later re-installation by yourself, please let us know as soon as possible.
Schedule
This work is expected to occur from Wednesday, February 23 to Friday, February 25.
Who can you call
Region of Peel
Melvin Gonzalez
Project Manager
289-541-5777
Abhijeet Basi
Regional Construction Inspector
647-824-9684
GMBP Consultants
Zoltan Tako
Contract Administrator
519-501-4161
Eric McLennan
Lead Construction Inspector
226-821-4064
Pacific Paving Limited
Pacific Paving Limited will do the work, under contract to the Region of Peel
Dino Marchioni
Project Lead
905-670-7730
Danny Jennings
General Site Superintendent
416-318-9015