Project 13-4055
Streets affected: Robertson Davies Drive/Cresthaven Road, Van Kirk Drive, McLaughlin Road, Petch Avenue/Queen Mary Drive, Edenbrook Hill Drive, Chinguacousy Road
Construction details
Peel Region is widening Mayfield Road from 2 to 6 lanes (3 lanes in each direction). This major project will significantly improve the road corridor for residents and will accommodate current and future growth in the area.
The work consists of road excavation, grading for widening, major culvert replacements, storm sewers not limited to catch-basins, oil grit separators and storm pipes, multi-use path, noise walls, curb and gutter, street lighting, intersection signalization, asphalt paving and final restoration.
Construction schedule
Start: Spring 2025 - Finish: End of 2026 (weather permitting)
Working hours
- Hours of operation are from 7 a.m. to 7 p.m., Monday to Friday.
- There may be weekend work to meet project deadlines.
- Extended hours may cause inconvenience but will help facilitate the completion of the project.
- These hours follow municipal by-laws.
Traffic control
- The project will be phased to minimize traffic disruption while maintaining a safe working environment as required under the Occupational Health and Safety Act.
- Existing traffic flows (2 lanes) will be maintained during construction.
- Due to the nature of the work, there will be instances of slowdowns, and as such, residents should expect delays.
- Use caution when travelling through the work zone.
- Emergency access will be maintained at all times.
Driveway access
- We will do our best to maintain driveway access. If a temporary blockage is necessary, we will contact property owners directly to coordinate the work.
- Businesses will have access at all times.
Staying informed
- Peel Region will keep you informed of any substantial changes in the project scope or schedule.
- Please contact the Project Manager if you have any special needs.
Ommar Moeen
Project Manager, Peel Region
Phone: 905-791-7800, ext. 7998
Email: construction@peelregion.ca
Asad Rauf
Construction Inspector, Peel Region
Phone: 905-791-7800, ext. 3246
Jason Okhowat Site Supervisor
KAPP Infrastructure Ltd.
Phone: 416-795-9393