Front Street Wastewater Pumping Station and Wastewater Diversion
Study background
In 2019, the Region of Peel completed a Schedule B Municipal Class Environmental Assessment (Class EA) Study to address wastewater flows from the Front Street Sewage Pumping Station (SPS) catchment area to align with the Region’s long-term sustainable plan to provide wastewater services. When the EA was completed, a Feasibility Study began to review alternate design configurations to maximize the Region’s investment. The Feasibility Study identified an additional opportunity to extend the Lakeshore Road sanitary trunk sewer across the Credit River from Jack Darling Memorial Park to east of the Credit River using trenchless technology. Also identified is an opportunity to move the proposed Richards Memorial Sewage Pumping Station to Jack Darling Memorial Park.
Based on the Feasibility Study, the Region of Peel is preparing an Addendum to the 2019 Class EA Study. The focus of the Addendum is the construction of a new pumping station at Jack Darling Memorial Park and the elimination of a new pumping station identified at Richard’s Memorial Park.
If you have any questions, feedback, or would like to be added to the study mailing list, please contact one of the team members:
Lyle LeDrew, C.E.T.
Project Manager, Engineering Wastewater Collection
Region of Peel
905-791-7800, ext. 7836
lyle.ledrew@peelregion.ca
David Abreu, P.Eng.
Project Manager
Region of Peel
416-274-9164
david.abreu@peelregion.ca
Neil Harvey, P.Eng., PMP
Consultant Project Manager
Stantec Consulting Ltd.
905-381-3234
neil.harvey@stantec.com
The Region of Peel is committed to ensure that all Regional services, programs, and facilities are inclusive and accessible for persons with disabilities. Please contact a Project Manager if you need any disability accommodations to provide comments or feedback for this study.
This notice was first issued on December 9, 2021.