Watermain replacement and improvements

Groveland Crescent, Groveland Court, Grenadier Road, Greenwood Crescent and Gulliver Crescent - Project 23-1340 D

The new watermains on Groveland Crescent, Groveland Court, Grenadier Road, Greenwood Crescent and Gulliver Crescent have now been installed. The next phase is to bring the new watermains into service. Properties on these streets will now have their individual water service pipes transferred from the old watermain to the new watermain.

A new water service pipe will be installed from the watermain to your property line, where a new water service box will also be installed. The water service box is a small round metal valve typically located in your driveway or lawn at the front of your property. Replacing your water service box requires digging up your existing water service box and disturbing an area at least two square meters.

Find a larger version of this image at peelregion.ca/water/your-home/

Where possible, your water service pipe will be installed using tunneling equipment. If tunnelling isn’t possible due to ground or environmental conditions, the contractor will need to dig a trench to install the new pipe.

Any damage caused by Regional construction will be repaired:

Interrupting your water supply

Connecting your property to the new watermain will require temporarily shutting off your water.

For residents:

If we must shut off your water due to an emergency, we will knock on your door to alert you, and do everything we can to fix the problem as quickly as possible.

Schedule

We expect to start connecting water service pipes to the new watermain around March 18, 2024. We expect to complete this work by April 26, 2024.

Once we have connected all properties to the new watermain, we will start repairing driveways, roads, curbs, sidewalks, and sod (grass).

Please note that repairs may be delayed due to contractor availability or weather conditions.

For example:

Repair work completed as part of this watermain replacement project is under warranty for two years from the completion date.

Driveway repairs

If you would like to have the rest of your driveway paved, please contact the contractor, Gio Contracting Inc., at 416-783-1446. The contractor will then share contact information for the company hired to do the paving repairs. Please remember this is your option. If you decide to have your entire driveway repaved, this extra paving work is your responsibility and outside the jurisdiction of Peel Region.

Temporary restoration on Groveland Crescent and Groveland Court

Your city is planning to complete roadwork on your street within the next few years. As this roadwork may impact the driveway, boulevard, street, curbs, and sidewalks, we will:

Peel Region’s repairs are temporary, as the city will complete restoration as part of their roadwork. Your city will send you a separate notice about their construction.

Contractor and working hours

The work will be completed by Gio Contracting Inc. under contract to Peel Region. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighbourhood to be under construction for a longer period of time.

What to expect during construction

Learn what to expect during watermain construction by visiting peelregion.ca/construction/watermain and watching our short video. The video goes behind the scenes to show what happens before, during and after construction. This website also answers common questions about:

Safety during construction

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/workzonesafety.

Staying informed

Receive timely project updates right to your inbox by signing up for e-notices. Visit peelregion.ca/construction/signup.

Information on this project can also be found at peelregion.ca/pw/construction/bram/23-1340D.asp.

We will try to disturb you as little as possible, and we will let you know if there are any major changes to the plans.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions or concerns, please contact us.

Water Linear Engineering
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca