Construction planning process

The construction phase of a project is the final stage of a planning process.

A project must complete 5 phases before construction begins.

Phase 1: The Environmental Assessment (EA) process

An environmental assessment (EA) is a study.

EAs predict, identify, measure and reduce how a project might affect the people, plants and animals living in a certain area.
EAs:

See which EAs are currently active in Peel.

Phase 2: The detail design phase

During the detail design phase, the Region:

The detail design phase can take up to 2 to 3 years to complete, depending on how complex a project is.

Phase 3: Property acquisition

An acquisition is the act of getting ownership or possession.
Property acquisition:

Phase 4: Utility relocation

Phone, hydro, gas and cable services in the construction area might need to be moved to complete a project.
If possible, utility relocation is completed before construction. When a utility relocation happens depends on how quickly the Region buys the land for the project.

Phase 5: Tender and contract award

A tender is a formal document that sets out the requirements of a construction project. The Region buys (procures) goods and services through tenders.
Contractors submit tenders for the work to be done. After evaluating all the tenders, the Region gives the job to the pre-qualified lowest bidder.
Contracts are usually awarded within 6 to 8 weeks from the time the tender is posted.

Construction begins

On average, a contractor starts construction 2 to 3 weeks after being awarded the contract. Construction can last from months to years depending on what’s involved.