Projects 18-1380 and 11-2380 - May 5, 2023 update
Street affected: Main Street South, Brampton
Road repairs and resurfacing (Stage 3)
The Region of Peel has been working in your neighborhood to replace the aging watermain and sanitary sewer along Queen Street. This work is required to maintain and improve existing water and wastewater services.
At this stage in the project, the Region of Peel will be replacing the watermain and sanitary sewer under Main Street South. Lane reductions will be required to complete this work.
Traffic impacts
- Northbound Main Street South will be closed to all through traffic from Wellington Street to Queen Street. A detour route will be clearly marked with road signs. Please see the attached map for the detour route. Pedestrian access to businesses will be maintained. No through traffic will be allowed and there will be no on-street parking.
- Southbound Main Street South will remain open but will be reduced to one lane from just north of Queen Street to Wellington Street.
- These traffic impacts are anticipated to start as early as Wednesday, May 10, 2023, and will last for approximately three months, depending on weather and soil conditions. Please expect delays and choose alternate routes if possible.
- It will be necessary to dig a temporary trench on Main Street South from Wellington Street to Queen Street. For this reason, it will not be possible to turn left (east) from Main Street South onto Wellington Street East.
- The current one-way traffic on John Street will be converted to two-way traffic that can be accessible from Chapel Street. The loading zones on John Street will be removed and additional loading zones/short term parking will be added to Queen Street for businesses.
- Detour routes may be adjusted for upcoming special events in the summer.
Emergency service vehicles will be permitted to cross through the closure with guidance from the onsite contractor. We apologize for any delays or inconvenience resulting from these traffic impacts.
Keeping you informed
Weather and other unpredictable events may change the date of these traffic impacts. Receive timely project updates right to your inbox by signing up for e-notices at peelregion.ca/construction.
Follow Peel Public Works on Twitter for project updates.
Information on this construction project can also be found at peelregion.ca/downtownbrampton.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/workzonesafety.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water and wastewater services. If you have any questions, please contact us.
Water Linear Engineering and Reliability
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409