Project 25-1340 D - July 24, 2025 update
Street affected: Salisbury Circle
Advance notice and pre-design field investigation
As part of the Flow | Central Brampton Program, Peel Region will be replacing the watermains in your area within the next two years.
Watermains are underground pipes that bring tap water from our water treatment facility to your neighbourhood.
As pipes age, we need to replace them to provide you with high-quality water.
Important note
Construction will take place in the municipal right-of-way and within easements.
- The municipal right-of-way includes the street and the municipal-owned land between the street and the water service box, a small, round, metal valve located outside on the property line between your home or business and the road.
- An easement is where Peel Region has legal access to enter your property to maintain and improve Peel’s infrastructure.
This work may impact the bottom of your driveway and the area around the sidewalk. We recommend that you delay major landscaping or driveway paving until construction is completed.
Before construction begins
Before we start construction, we will be in your area conducting field investigations along Salisbury Circle.
- We will survey your street and use temporary spray paint or flags on roads, driveways, and lawns to locate underground gas, hydro, and cable.
- We may drill holes in the road or municipal right-of-way to collect soil samples, determine ground conditions, or confirm utility locations. The municipal right-of-way includes the street and the municipal-owned land between the street and the water service box, a small, round, metal valve located outside on the property line between your home or business and the road.
- We will take pictures and videos to help restore the area as close as possible to its former condition, after construction takes place.
We expect these activities to happen between August 5, 2025, and August 15, 2025.
Consultant working hours
The work will be completed by EnVision Consultants Ltd. under contract to Peel Region. Working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with local municipal bylaws.
Traffic impacts
There may be minor traffic disruptions during these activities. If this is needed, we will place signs giving directions.
What to expect during construction
Refer to our short video to learn what to expect before, during, and after watermain construction. The video also answers common questions about:
- Why your water may be temporarily shut off.
- How traffic, parking, and waste collection may be affected.
- How driveways, roads, and sod (grass) are repaired.
Temporary park closures
Temporary closures may be required within Salisbury Circle Parkette.
Keeping you informed
We’re currently in the early planning stages, so we cannot give exact dates. As your city’s future planning activities may change, we may also update our plans to replace watermains. We’ll deliver more detailed information closer to the start of construction.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
- More information on the Flow Program can be found on the program webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide safe drinking water to support a thriving community for life.
Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca