Project 24-1370 A - October 31, 2025 update
Streets affected: Heather Street, Terry Street, Kentbridge Court and Vaughan Court
Notice of restoration
Peel Region will be repairing driveways, roads, curbs, sidewalks, and sod (grass), following the replacement of the watermains along Heather Street, Terry Street, Kentbridge Court and Vaughan Court.
Restoration schedule
Restoration work will start in November at Kentbridge Court. Then during the same month, we expect to start restoration work on Vaughan Drive, Heather Street and Terry Street. We plan to complete all work by December 2025, weather permitting.
Restoration will begin by fixing curbs and sidewalks, followed by driveway and road paving repairs, and finally sod replacement. This will take approximately four weeks.
Please note that repairs may be delayed due to contractor availability or weather conditions. For example:
- Paving cannot take place when the ground is saturated with water, or the temperature is below 3C.
- Asphalt is not available in large volumes during the winter. It usually becomes available around mid-May.
- Most sod farms are located north of Peel. They usually have sod available starting in late May. We’ll replace the sod on your property once it is available.
- In summer, we may need to postpone sod replacement due to hot, dry weather.
- We replace sod only until the middle of November, weather permitting, to let the sod grow roots. If we do not repair your lawn by the middle of November, we’ll replace the sod the following spring.
Contractor working hours
The work will be completed by Ground Breakers Contracting under contract to Peel Region. Working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with local municipal bylaws and help shorten the amount of time construction is in your neighborhood.
Traffic and parking
We may need to temporarily close roads or reduce traffic to a single lane. If this is needed, we will place signs giving directions. On-street parking will be reduced when we are working on your street.
Construction safety
Construction zones require extra caution to keep everyone safe. Be aware of your surroundings when driving, walking, or biking near the construction area. Watch for construction crews and other road users, slow down, and consider other routes. Learn how to stay safe in construction zones.
In-ground sprinkler systems
If the area in front of your home was affected by construction, in-ground sprinkler lines may be impacted during the upcoming restoration work. We strongly recommend moving any sprinkler lines in the municipal right-of-way or next to the sidewalk. The municipal right-of-way includes the street and the municipal-owned land between the street and the water service box, a small, round, metal valve located outside on the property line between your home or business and the road.
If you cannot move these sprinkler lines, send us your irrigation map or flag each sprinkler head within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.
Driveway access and parking
We may block your driveway for a short time to pave the road. We’ll ensure businesses can be accessed when possible. Contact us if you have any access needs.
Please avoid parking on your driveway when it is being repaired. We’ll knock on your door before driveway work begins. If you will not be home weekdays between 7 a.m. and 7 p.m., do not leave any vehicles on the driveway. Avoid driving on new asphalt for the first three hours and parking on it for one day after paving.
Residents are encouraged to apply for a temporary parking pass from the Town of Caledon to park on streets outside the construction area for alternate parking.
Replacing grassy areas
The contractor will replace any damaged sod on the boulevard or your front lawn and will take care of it for 30 days. You can help the sod stay healthy by watering it. A longer watering works better than watering more frequently for a shorter time. Early morning watering allows more water to soak in.
Repairing driveways
- Interlock or concrete driveways: If we damage a portion of your driveway, our contractor will repair the damaged portion.
- Asphalt driveways: If we need to cut a section of your driveway, it will be repaired by paving a strip over the impacted area, resulting in minimal seams. Peel cannot replace your entire driveway. If you would like to have the rest of your driveway paved, please contact the contractor, Ground Breakers Contracting, at (416) 559-2313. The contractor will then share contact information for the company hired to do the paving repairs. Please remember this is your choice. If you decide to have your entire driveway repaved, this extra paving work is your responsibility and outside Peel Region jurisdiction.




Repairing roads
We'll pave the road where it was affected by construction. This work will start around November 6, 2025, weather permitting. We’ll deliver more detailed information closer to the start date.
Warranty on construction repairs
All work is under warranty for 2 years from the completion date.
It is normal for repaired areas to settle. Let us know if you notice large potholes forming where the driveway, street, or lawn was repaired, and we’ll ensure these are fixed before the warranty period ends. Once the warranty period is over, Peel is no longer responsible for fixing potholes or dead sod in these locations.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel's world-class water systems, allowing us to provide safe drinking water to support a thriving community for life.
If you have any questions, contact us.