Project scope
Peel Region will be replacing noise attenuation walls on Steeles Avenue West in 2025. The detailed design is underway, and we are considering options to expedite this project.
The locations of the new noise attenuation walls, along Steeles Avenue West, are as follows:
- Mclaughlin Road to Windmill Boulevard
- 680 metres west of Windmill Boulevard
Next steps
Construction is scheduled for Summer 2025 and will include the following:
- Remove existing noise walls at the rear/side of the properties
- Construct temporary fencing to isolate the construction area from the remainder of the yard to maintain the security and privacy of your yard
- Construct the new noise wall
- Perform restoration on public and private sides
Immediately prior to construction, you will receive an additional notification regarding the timing of the project.
Feedback results
This is the summary of the results received from the participants that provided feedback for the noise walls preference at Steeles Avenue West noise wall replacement Chinguacousy Road to McLaughlin Road:
- Composite concrete: 86%
- Cedar wood: 5%
- Indifferent (fine with either option): 8%
Based on the feedback results, the majority of the participants prefer Composite Concrete noise walls.
For any questions about the survey results or the project, please contact:
Adam Banaszek,
Project Manager
Peel Region
Phone: 905-791-7800
Mansoor Khorsand, P.Eng.
Project Manager,
Saferoads Engineering
136 Centre St.
Aurora, ON L4G 1K1