Project 23-1160 – June 26, 2026
Streets affected: Attmar Drive and The Gore Road
Project update
Peel Region is installing a sanitary sewer along Attmar Drive and The Gore Road. Under the City of Brampton Noise Bylaw, tunneling work is allowed to take place continuously, 24 hours a day, 7 days a week to reduce the impact of our work.
Schedule
This 24/7 work is expected to start early July 2026 and finish by September 2026. During this time, we do not anticipate any significant noise. Materials will be delivered and removed between 7 a.m. and 7 p.m. to minimize impacts.
Construction safety
Construction zones require extra caution to keep everyone safe. Be aware of your surroundings when driving, walking, or biking near the construction area. Watch for construction crews and other road users, slow down, and consider other routes. Learn more about how to stay safe in construction zones.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide safe drinking water and reliable wastewater services to support a thriving community for life.
Water Linear Engineering & Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Peel Region
Phone: 905-791-7800 ext. 4409