Project 22-4685
Asphalt resurfacing on The Gore Road
Streets affected: Healey Road to King Street
Project update
We have finished the work. The project is under warranty until November 2026.
Where is the work happening
- On The Gore Road, from Healy Road to King Street in the Town of Caledon.
- Project Area Diagram
What are we doing
The work includes:
- The removal and replacement of asphalt pavement.
- The removal or granular shoulder and replacement with asphalt shoulder.
- The removal and replacement of steel beam guide rails.
- Intersection improvements and traffic signal modifications.
When
- Construction Start: August 2024 – Finish: October 2024 (weather permitting).
Working hours
- Four Seasons Site Development Ltd. Has been contracted to complete the work on Peel Region’s behalf. Hours of operation are from 6 a.m. to 7 p.m., Monday to Friday.
- Work may also be done on Saturdays.
- These hours follow city by-laws. Extended working hours may cause inconvenience but will allow the project to be completed as quickly as possible.
Traffic control
- The project will be phased to minimize traffic disruptions while maintaining a safe working environment as required by the Occupational Health and Safety Act.
- Existing traffic flows will be maintained during construction. However, due to the nature of the work, we’ll need to reduce traffic to a single lane and temporarily block intersections during construction.
- Emergency access will be maintained at all times.
- Please use caution when travelling through the work zone.
Driveway access
- We will maintain driveway access as much as possible. If we need to temporarily block your driveway, we will contact you to arrange a time.
- We will ensure businesses always have access.
Project updates
- Peel Region will keep you informed of any substantial changes in the project scope or schedule.
- Please contact the Project Manager if you have any special needs.
Who can you call
Umair Keen
Project Manager
Peel Region
905-791-7800 ext. 1401