Project 20-4517 Steeles Avenue
      
  Steeles Avenue noise attenuation wall replacement from Hartford Trail to Hurontario Street.
    
  We have finished the work. The project is under warranty until March 31, 2027.
Where is the work happening
- On Steeles Avenue East from Hartford Trail to Hurontario Street.
 
What are we doing
The work includes:
- Clearing and grubbing;
 - Tree pruning and removal;
 - Removal and disposal of existing noise wall and/or fence;
 - Installing temporary fence;
 - Installation of new noise attenuation wall;
 - Extension of existing backyard fences to new noise attenuation wall;
 - Restoration, and minor related works.
 
When
- Construction Start: Oct 2024 – Finish: Summer 2025 (weather permitting)
 
Working hours
- Anthony Furlano Construction Inc. has been contracted to complete the work on the Region’s behalf. Hours of operation: 7 a.m. to 5 p.m., Monday to Friday.
 - These hours follow the city’s by-laws.
 
Traffic control
- Temporary lane closures will be required during non-peak hours.
 - Emergency access will be maintained at all times.
 - Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.
 
Driveway access
- We anticipate no impact to any driveway access.
 
Project updates
- Peel Region will keep you informed of any substantial changes in the project scope or schedule.
 - We are committed to ensuring minimum disruption to your homes.
 - Please contact the Project Manager if you have any special needs.
 
Who can you call
Nabiel Matta
Project Manager
Region of Peel
Phone: 905-791-7800 ext. 7862