Project 19-4060 - June 29, 2026 update
Streets affected: North of Cranston Drive to north of Huntsmill Drive, and Old Church Road, from Airport Road to Marilyn Street (East)
Road closure notice
Airport Road will be closed for through-traffic from Emma Street to Hilltop Drive, effective July 6 to September 7, 2026.
As part of the improvement of Airport Road, Peel Region will be removing and widening the existing bridge culvert at the Caledon Trailway and will be installing large-diameter storm pipes. To ensure the safety of the public and to expedite the duration of construction, Airport Road will be closed from Emma Street to Hilltop Drive.
Access to residents and businesses will be fully maintained through local detours.
Construction and closure schedule
The Airport Road Improvement project is anticipated to be completed by the end of 2027. The bridge and large-diameter storm works from the Centreville Creek Bridge to Hilltop Drive will begin on July 6, 2026, and will be completed by September 7, 2026.
Traffic control
Airport Road will be closed for through traffic between Olde Base Line and Emma Street, coinciding with the truck prohibition program that will start on July 1, 2026. Local access to residents and businesses will be permitted from either end of the closure limits. Access for emergency services will be maintained.
Caledon Trailway crossing
During the bridge works, the crossing on Airport Road will be closed. Trail users will need to follow signage posted East and West of the trail and along the detour route to get back on the trail, and to safely cross Airport Road.
Contact
Peel Region will have a field representative on site (construction inspector) during construction. Should you require assistance during construction, please reach out to the construction inspector or project manager directly.
Joe Partipilo
Construction Inspector, Peel Region
Phone: 437-925-2661
Bassem Ghoneim
Project Manager, Peel Region
Phone: 437-233-5173
24 hours a day, 7 days a week project related emergency and after hours contact: 905-791-7800
Project updates
Peel Region is committed to keeping you informed and ensuring that this work is carried out with minimum disruption to your homes and businesses. Refer to the project webpage for the most up-to-date project information and key milestones.