Project 19-2410 April 10, 2025 update on Ninth Line
Streets affected: Ninth Line
Previous notices
- April 9, 2025 – traffic closure update
- February 20, 2025 – construction commencement on Ninth Line
- January 28, 2025 – construction commencement
Peel Region has been working in your neighbourhood to rehabilitate the existing sanitary sewer system and maintenance holes (commonly called manholes) along Ninth Line. This work is required to maintain and improve existing wastewater services.
Traffic impacts
Temporary Road closures on Ninth Line at the following locations have been updated as follows:
April 21 to April 23, 2025
- Tacc Drive will be closed to all through traffic at Ninth Line.
- Map of Tacc Drive road closure
April 23 to May 16, 2025
- Deepwood Heights will be closed to all through traffic at Ninth Line.
- Talias Crescent will be closed to all through traffic from 3883 Talias Crescent to 3859 Talias Crescent. Residents who live on Talias Crescent will have access to their homes.
- Janice Drive will be closed to all through traffic at Ninth Line.
- Henrietta Way will be closed to all through traffic at Ninth Line.
- Maps of Deepwood Heights, Talias Crescent, Janice Drive, and Henrietta Way road closures
May 16, 2025
- Tacc Drive will be closed to all through traffic at Ninth Line.
- Map of Tacc Drive road closure
A detour route will be clearly marked with road signs.
We apologize for any delays or inconvenience resulting from these traffic impacts.
Get the latest project updates
We will let you know if there are any major changes to the plans. Receive timely project updates right to your inbox by signing up for e-notices.
Information on this project can also be found on the project webpage.
We understand that construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world class water system, allowing us to provide reliable wastewater services to support a thriving community for life. If you have any questions, please contact us.
Condition Assessment and Rehabilitation
Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409