Project 18-2300 C - December 20, 2022 update
Streets affected: Fair Birch Drive and Birchview Drive, Mississauga
The Region of Peel has been working in your neighborhood to replace the aging sanitary sewer just north of Fair Birch Drive, along the Lornewood creek water course. This work is required to maintain and improve existing wastewater services.
At this time, we have:
- Installed a new sanitary sewer along Birchview Drive from Fair Birch Drive to Lornewood Creek,
- Set up tunnel access points on Fair Birch Drive to facilitate tunneling the new sewer along Fair Birch Drive.
Project update
We will be shutting down for the winter break on December 23, 2022 and will restart work on January 3, 2023. We will leave the construction site in a safe condition during this period and provide ongoing maintenance as necessary.
Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices.
Keeping you informed
We will let you know if there are any major changes to the plans.
Information on this project can also be found on the project webpage.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn more about how to stay safe in construction zones.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality wastewater services. If you have any questions, please contact us.
Wastewater Collection and Conveyance, Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409