Project 13-1347H3 - July 21, 2023 update
Sheridan Park Pedestrian Path Closure.
The Region of Peel has been working in your area to construct new station piping at the Herridge Pumping Station and Reservoir in Sheridan Park. This work is required to maintain and improve existing water services.
Construction schedule
Construction began on June 19, 2023 and will be completed in September 2023. These timelines are estimates, as weather and other unexpected events may impact our timelines.
Pedestrian impacts
To keep pedestrians safe during this construction work, the Sheridan Park pedestrian path south of the Herridge Pumping Station and Reservoir will be closed from Varency Drive to Sheridan Park, as shown on the attached map. This section of the trail will be closed from Wednesday, July 26, 2023 until Friday, August 18, 2023, weather dependent.
Keeping you informed
We will let you know if there are any major changes to the plans.
Receive timely project updates right to your inbox by signing up for e-notices.
Information on this project can also be found on our project webpage.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions, please contact us.
Water Linear Engineering
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409