Temporary asphalt sidewalk installation on Dixie Road, north of Mayfield Road.
Where is the work happening
What are we doing
The work includes:
- Grading and shoulder stripping.
- Installation of temporary asphalt sidewalk.
- Supply and install precast concrete curbs and flexible bollards.
- Ditching and pavement markings.
- Installation of temporary lighting for illumination.
When
- Construction Start: August 2025
- Construction Finish: October 2027 (weather permitting)
Working hours
- Pacific Paving Ltd. has been contracted to complete the work on Peel Region’s behalf.
- Hours of operation are from 9:00 a.m. to 7:00 p.m., Monday to Friday and work may also be done on Saturdays.
- These hours follow the Town of Caledon by-laws. Extended working hours may cause some inconvenience to the public, however, will help to facilitate the completion of the project as quickly as possible.
Traffic control
- The project will be phased to minimize traffic disruption while maintaining a safe working environment as required under the Occupational Health and Safety Act.
- Existing traffic flows will be maintained during construction. However, due to the nature of the work, we will need to narrow traffic lanes.
- The Speed limit will be reduced to 50km/h within the construction zone.
- Emergency access will be maintained at all times.
- Please use caution when travelling through the work zone.
Driveway access
- We will maintain driveway access as much as possible and if we need to block your driveway for a short time, you will be contacted to arrange for the best time.
- We will make sure businesses have access at all times.
Project updates
- Peel Region will keep you informed of any substantial changes in the project scope or schedule.
- Please call the Project Manager if you have any special needs.
Who can you call
Nour Tabieh
Project Manager
Peel Region