Notice of addendum completion - October 3, 2025
Background
Peel Region has completed a Schedule C Municipal Class Environmental Assessment (MCEA) Addendum study for proposed watermain upgrades from Stillmeadow Road to Dixie Road in the City of Mississauga. In 2022, the Region completed a Schedule C Municipal Class EA for the Wastewater Capacity Improvements in Central Mississauga which included the Queensway East Trunk Sewer (QET). Since the completion of the EA, the Region identified the need to increase the resiliency and capacity of the water pressure system in the area (Zone 2) to service future growth and ensure continued alignment with the Region’s long-term plan for providing water service. The Region of Peel has prepared an Addendum to the 2022 Class EA study that includes the following preferred solution for the watermain upgrades:
- Full pipe replacement of the Queensway watermain from Stillmeadow Road to Haines Road and extension of the watermain to Dixie Road.
This work will be completed underground in a tunnel below the Queensway with tunnel access points at various locations which are outlined in the Addendum Report. Construction impacts and traffic management will be limited to the areas of the tunnel access points and will be further reviewed and confirmed during detailed design.
Public comment period
The Addendum Report will be available for a 30-day public comment period starting October 3, 2025 until November 1, 2025, in accordance with the requirements of the Municipal Class EA process (MCEA, February 2024). If you would like a copy of the report, please contact the Project Manager.
We invite you to review the report and provide written comments and concerns by November 1, 2025 directly to:
Sarah Lobo, P.Eng.
Project Manager
Water & Wastewater Engineering Services Division Public Works, Region of Peel
905-791-7800, ext. 8266
For concerns that involve the prevention, mitigation, or remediation of adverse impacts on constitutionally protected Aboriginal and treaty rights, a Section 16 Order request may be made to the Ministry of the Environment, Conservation and Parks. Section 16 Order requests on other grounds will not be considered. Requests should include your full name and contact information. Requests should specify what kind of order is being requested (imposing additional conditions or requiring a comprehensive environmental assessment), the project name, explain how an order may prevent, mitigate, or remedy potential adverse impacts, and can include any supporting information.
Requests must be sent to the Ministry by November 1, 2025, and should be sent in writing or email to both:
Hon. Todd McCarthy
Ministry of Environment, Conservation and Parks 777 Bay Street, 5th Floor
Toronto ON, M7A 2J3
Director, Environmental Assessment Branch
Ministry of Environment, Conservation and Parks
125 St. Clair Ave. W, 1st Floor
Toronto ON, M4V 1P5
A copy of the request should also be sent to the Region’s Project Manager, Sarah Lobo.
Personal information collected on this subject is collected under the authority of the Freedom of Information and Protection of Privacy Act. The Region of Peel is committed to ensuring that all Regional services, programs, and facilities are inclusive and accessible. Please contact the Project Manager if you need any accommodations to provide comments and/or feedback for this study.
With the exception of personal information, all comments will become part of the public record of the study. The study is being conducted according to the requirements of the Municipal Class Environmental Assessment, which is a planning process approved under Ontario’s Environmental Assessment Act.
This notice was first issued on October 3, 2025. The commenting deadline closes November 1, 2025.