Notice of Public Information Centre No. 3 – December 11, 2025
Background
Peel is growing, and we want to ensure our community remains a great place to live, work and play. Peel’s Flow | Central Brampton Program is advancing 30+ essential water and wastewater infrastructure projects, faster, throughout Brampton.
The province has committed to building 1.5 million more homes in Ontario over the next decade—with 113,000 in Brampton. These provincial housing targets have significantly increased the demand for water, wastewater and road infrastructure.
Flow | Central Brampton will meet these demands by combining more than 30 water and wastewater projects into one large-scale construction program across Brampton, including the Schedule C Municipal Class Environmental Assessment (MCEA) Study for the Kennedy Road Sanitary Trunk Sewer Project. This Project will help ensure sewage capacity requirements are met by 2051 to support growth in Peel Region. Refer to Figure 1 for Project Study area, including the recommended preferred route.
Process
This study has been following the 2024 process for a Schedule “C” MCEA project, which includes:
- Indigenous community engagement and public and stakeholder consultation
- Background studies
- Development, evaluation, and selection of sewer route options, impact assessment and mitigation measures
- Development, evaluation, and selection of the preferred sewer construction methodology, including shaft locations
Public Information Centre #3
We invite you to join us for Public Information Centre #3, where we will present the results of the completed evaluation of construction methods and shaft locations, with opportunities to provide feedback and ask questions.
All materials will be posted online, including a survey open until January 5, 2026.
- When: Thursday, December 11, 2025, from 6:00 p.m. to 8:00 p.m.
- Where: Paul Palleschi Recreation Centre (30 Loafers Lake Lane, Brampton ON L6Z 1X9), Meeting Room 2
Once the study is complete, results will be published in an Environmental Study Report (ESR) and will be made available for public review and comment.
We invite you to attend the Public Information Centre, review the materials posted on the Project website and respond to the survey.
Figure 1: Project study area and selected route
Kennedy Rd sanitary trunk sewer project map
Contact the team
To be added to the mailing list or to receive further information about the study, contact:
Italia Ponce, P.Eng.
Project Manager, Region of Peel
Tel: 905-791-7800 ext. 4583
Faranak Amirsalari, MES, MCIP, RPP
Environmental Planner, AECOM
Tel: 416-420-1286
The Region of Peel is committed to ensuring that all Regional services, programs, and facilities are inclusive and accessible. Please contact the Project Manager if you need any accommodations to provide comments and/or feedback for this study.
With the exception of personal information, all comments will become part of the public record of the study. The study is being conducted according to the requirements of the Municipal Class Environmental Assessment, which is a planning process approved under Ontario’s Environmental Assessment Act.
This notice was first issued on November 27, 2025.