Notice of Public Information Centre 2 - May 29, 2024
Background
The Region of Peel is conducting the Bolton Water and Wastewater Capacity Improvements Municipal Class Environmental Assessment (MCEA) study. This MCEA builds off a Feasibility Study recently completed by the Region which outlined conceptual water and wastewater projects that service the additional development proposed within both the intensification and greenfield growth areas in the Community of Bolton. Additionally, the MCEA will complete a comprehensive evaluation of all potential alternatives to develop the optimal water and wastewater servicing solutions to meet existing needs and growth within the Bolton study area.
Process
The study follows a Schedule ‘C’ Class EA process, including:
- Consultation with Indigenous Rights Holders
- Engagement with Indigenous stakeholder, agencies, and the public
- Investigating alternative water and wastewater servicing strategies, routes, and design concepts
- Confirming the preferred solution including alignments, siting, design, and construction timing
Your input is important
Public Information Centre (PIC) No. 1 was held on November 16, 2023, and presented the study objective, Class EA process and the evaluation and selection of the focus areas. PIC materials can be found on the project webpage.
Two additional PICs are planned for this project.
PIC No. 2
Date and time: Wednesday, June 12, 2024, from 5 p.m. to 7 p.m.
Location: Albion Bolton Community Centre - Room C, 150 Queen St. South, Bolton
PIC No. 2 will be conducted in person and will cover the evaluation of alternative solutions. We will also present the selected preliminary preferred servicing solution, including details such as the location of a new sanitary pumping station, sanitary forcemains and sewer alignments and watermain alignments. Information will be displayed on boards, and staff will be available to answer questions and discuss next steps in the study. Please come join us!
PIC No. 3 is planned for Fall 2024 and will be completed and published at a later date.
Contact
To be added to the mailing list or to receive further information about the study, please contact:
Italia Ponce
P.Eng., Project Manager, Region of Peel
10 Peel Centre Drive, Suite A, 4th Floor, Brampton, ON, L6T 4B9
Tel: 905-791-7800 ext. 4583
PIC No. 3 is planned for Fall 2024 and will be completed and published at a later date.
- This notice was first issued on May 29, 2024