Contractor evaluations
Performance evaluations:
- Provide an assessment of a vendor’s performance on any awarded contract subject to a Vendor Performance Evaluation process.
- Will become an official record to be kept in accordance with the Retention and Validity Period guidelines
We evaluate our contractors’ performance in the following areas:
- Project commencement
- Project management
- Workmanship
- Safety
- Contract management and Supervision
- Client and public relations
- Project completion
If you have any questions about this procedure, e-mail Vendor Performance.
Disclosure and compliance
The Region reserves the rights to share the results of any evaluation with other municipalities or government bodies upon request, where the Vendor has listed the Region as a reference, or otherwise at the discretion of the Region.
Information to be shared shall include, but not be limited to, the following: final score, Litigation history, Vendor issues, etc.
Any employee who knowingly contravenes any of the requirements of this procedure is committing an act of misconduct and is liable for the purchase as well as disciplinary action
The information collected in an evaluation will:
- Provide feedback to Vendors for performance improvements and/or acknowledge Satisfactory performance,
- Determine a Vendor’s eligibility or ineligibility to bid on future Region of Peel Contracts, and
- Provide justification for the award or non-award of Contracts.
A Vendor’s rating is based on the scoring of the criteria shown on the Evaluation Form.
This procedure should be read in conjunction with the Procurement By-Law, as amended from time to time.
The Region requires all Project Leads responsible for managing Contracts to complete the required evaluations in accordance with this procedure, as amended from time to time.
Calendar Day
All days in a month, including weekends and holidays.
Contract
The agreement in writing governing the performance of the Work and includes, without limitations, the Request for Tender, Request for Proposal, Direct Negotiation, Request for Quotation, Vendor’s Submission, and other written documents accumulated before or during the performance of the Contract outlining the requirements of the Work performed.
Contractor Performance Evaluation Form
The Evaluation Form specific to evaluating Work, performed by a Vendor including, but is not limited to, new construction, upgrades, renovations, etc.
Evaluation Form
The tool used to evaluate the performance of the Vendors. It outlines the specific Key Performance Indicators (KPIs) and their respective evaluation criteria.
Final Evaluation
The Final Evaluation to be completed under any Contract which summarizes the Vendor’s performance from the beginning to the end of the Contract duration. In the case of construction projects, this is completed at Substantial Performance.
Interim Evaluation
Any Performance Evaluation Form which is completed at any time after the commencement of the Work and prior to the Final Evaluation.
Litigation
Any issued lawsuit or administrative tribunal application in which the Vendor is involved with the Region, either as plaintiff, applicant, defendant or respondent, or any correspondence in contemplation of same.
Pre-Qualification
A request by the Region preceding a Request for Proposal, Request for Quotation, or a Request for Tender seeking submissions from potential Vendors where it is deemed that the nature and complexity of the work involved warrants the time and effort required to pre-select the most experienced and qualified Vendors.
Probation
A Vendor’s ability to bid on Region Contracts is limited until such time that the Vendor achieves a Satisfactory Rating.
Project Lead
The Region’s assigned individual who has the responsibility and authority for the planning, managing, executing, and closing of the Work associated with the Contract.
Rating or Status
The score received on a Final Evaluation is used to determine a Vendor’s standing as Satisfactory, Probation, or Suspension.
Satisfactory
Vendors who receive a Satisfactory Rating are eligible to bid on and be awarded Work for the Region, subject to other requirements of the Contract.
Subcontractor
A person, partnership, or corporation undertaking the execution of a part of the Work by virtue of an agreement with the Vendor.
Suspension
The Vendor is no longer permitted to bid on certain Region Contracts until permission is granted by the Region.
Substantial Performance
The Vendor has received the Certificate of Substantial Performance (as defined by Ontario Provisional Standards, Canadian Construction Documents Committee, or the Contract) as issued by the Project Lead.
Validity Period (Record)
Each Evaluation completed shall remain on the Vendor’s record for a period of 5 years, after which it will remain on file but will not be taken into consideration when determining any potential Suspension duration.
Vendor
For this procedure, an individual, partnership or corporation offering goods and services including but not limited to contractors, consultants, suppliers, and service organizations; understanding the Work as identified in the Contract where the Contract requires the completion of an Evaluation Form.
For the purposes of a Vendor’s eligibility or ineligibility to bid pursuant to Probation Rating and Suspension Rating, “Vendor” includes any entity affiliated or related to the Vendor (including any entity with the same directing mind as the Vendor on Probation or Suspension) as determined in the discretion of the Director of Procurement, in consultation with the Regional Solicitor.
Vendor Performance Evaluations (Evaluations)
The use of KPIs to capture, measure, analyze and report a Vendor’s performance on any given Contract to make a formal determination of a Vendor’s Rating.
Work
The work to be undertaken by the Vendor pursuant to the provisions of the Contract.
Project Leads
Project Leads are responsible for the management of Contracts and are therefore responsible for the completion of the Evaluation Form.
The Evaluation Form is a contractual requirement, and the subsequent completion of it is mandatory for all Project Leads.
If consultants, inspectors, or any other individual or organization was heavily involved in the management of the Contract and the Vendor, Project Leads may receive input from those individuals.
Procurement
Procurement is responsible for the collection, retention and reporting of data as well as ongoing maintenance and improvements including, but not limited to, procedure, Evaluation Forms, responding to inquiries, and providing support to Project Leads.
Additionally, Procurement shall ensure that the appropriate Vendor Performance Evaluation clauses are included in the development of any Contracts.
This section provides information and procedures involved in specifically administrating the Contractor Performance Evaluation Form.
Procedure
The following outlines the steps necessary for Project Leads to administer the Contractor Performance Evaluation Form:
- Where Contracts are externally managed, ensure that consultants are aware of this procedure and Contractor Performance Evaluation Form.
- Include the Contractor Performance Evaluation Form as a standing item on meeting agendas. Project Leads are to review performance status with the Vendor at site meetings and these discussions shall be captured in the meeting minutes, especially when there are concerns or issues surrounding the Vendor’s performance.
Completion of Interim Evaluations are required to be conducted by the Project Lead as follows:
Project Duration Frequency of Interim and Final Evaluation(s) Up to one month A Final Evaluation at the end of the project. One to 3 months A Final Evaluation at the end of the project with one Interim Evaluation. 3 to 6 months A Final Evaluation at the end of the project with one to 2 Interim Evaluations. 6 to 12 months A Final Evaluation at the end of the project with one to 3 Interim Evaluations. Over 12 months A Final Evaluation at the end of the project, one mandatory Interim Evaluation, with up to 3 Interim Evaluations per year. If a Vendor is on Probation Status, an Interim Evaluation must be completed after 6 months if the Work is still ongoing.
If a Vendor has completed its Suspension period and has ongoing Work, an Interim Evaluation must be completed at the completion of the Suspension period.
Procurement must be provided with a copy of the completed Interim Evaluation and shall be responsible for updating the Vendor.
*The number of interim evaluations to be completed on projects less than 12 months may be increased/decreased at the direction of the Project Lead’s Program Director.
While the above Interim Evaluations are mandatory regardless of the Contract duration, if there are issues with the Vendor, the Project Lead shall be required to complete Interim Evaluations on a regular basis.
Upon Substantial Performance, the Project Lead shall complete and sign the Final Evaluation after which the Project Lead shall route it for final approval and signatures as follows:
Rating Final approval Satisfactory Rating (70% or above) Project Lead’s direct Manager or Supervisor. Suspension or Probationary Rating (69% or below) Project Lead’s direct Manager or Supervisor and Director of the Division - The Final Evaluation, once approved, must be completed and delivered to Procurement within 60 Calendar Days of Substantial Performance.
- If the Final Evaluation is Satisfactory, the Project Lead shall submit to the Vendor a copy of the signed Evaluation Form via e-mail and copy vendorperformance@peelregion.ca.
- Where an Evaluation is not Satisfactory, the Project Lead shall review the Final Evaluation with Procurement and both parties shall present the Final Evaluation to the Vendor in person to review the deficiencies.
- Should the Agency or Vendor choose to terminate a Contract for any reason after the commencement of Work, or should the Agency terminate the Vendor’s right to continue performance of the Work under the Contract, the Contract Manager will complete a Final Evaluation within 14 Calendar Days of notice of termination. This Evaluation Score will determine the Vendor’s Status.
Upon completion of each Final Evaluation, the score calculated shall determine the Vendor’s Rating and their eligibility to bid on future Contracts as outlined below.
Satisfactory rating
Vendors who score 70% or above on the Final Evaluation are in Satisfactory Status and are eligible to bid on, and be awarded Work for the Region, subject to other requirements of the Contract.
Probation rating
Vendors who score between 60% and 69% or have just come off a Suspension, are deemed to be on Probation. The terms of Probation are dependent on whether or not the Vendor has other ongoing Contracts with the Region, and shall be as follows:
No Other Ongoing Contract(s) with the Region
The Vendor is eligible to bid on new Contracts and be awarded a maximum of one, subject to the requirements of the Contract. After award of the one Contract, the Vendor is not eligible to bid on any other Contracts until they are evaluated at Substantial Performance or an Interim Evaluation 6 months after mobilization, whichever comes first.
If the Vendor receives a Satisfactory Rating on the Final Evaluation or on its 6 months Interim Evaluation, the Vendor will move immediately into Satisfactory Status and the Probation Rating removed.
If the 6-month Interim Evaluation is anything but Satisfactory, the Vendor shall stay on Probation until the Final Evaluation is complete and subsequent Rating applied.
If the Vendor fails to receive a Satisfactory Rating on the Final Evaluation regardless of the Evaluation score, the Vendor shall move immediately into Suspension.
Ongoing Contract(s) with the Region
The Vendor is unable to bid on any new Contracts and must receive a Satisfactory Rating on all ongoing Contract(s) on either the Final Evaluation(s) or on an Interim Evaluation(s), whichever comes first, which is completed 6 months into the Probation period if mobilization has taken place, if not, it will be done at 6 months after mobilization.
If the Vendor receives a Satisfactory Rating on the Final Evaluation(s) or on its 6-month Interim Evaluation(s) the Vendor will move immediately into Satisfactory standing and the Probation Rating removed.
If the 6 month Interim Evaluation(s) is anything but Satisfactory, the Vendor shall stay on Probation until the Final Evaluation(s) are complete and subsequent Rating applied.
If the Vendor fails to receive a Satisfactory Rating on the Final Evaluation(s) regardless of the Evaluation score, the Vendor shall move immediately into Suspension.
While on Probation, Vendors shall be allowed to work as a Sub-Contractor on other Contracts, unless the Region deems otherwise.
Suspension rating
Vendors who score 59% or below on a Final Evaluation, or have just failed their Probation Status, will be placed on immediate Suspension, and shall not be allowed to bid on new Contracts for the durations outlined as follows:
- If this is the Vendor’s only Suspension on Record as per the Retention and Validity Period, the Vendor must complete a one year Suspension period.
- If the Suspension is the Vendor’s second or more Suspension on Record as per the Retention and Validity Period, the Vendor must complete a 3-year Suspension period.
Upon completion of any Suspension period the Vendor shall move into Probation Status.
While on Suspension, the Vendor shall not be allowed to perform any Work on any Region Contracts as a Subcontractor.
It is the responsibility of Vendors to ensure any Subcontractors they retain are in good standing with the Region and are eligible to perform work on Region Contracts prior to bidding on any Work.
Vendors are to call 905-791-7800 ext. 7538 to obtain an up-to-date list of any Suspended Subcontractors.
Should a Vendor name any Subcontractor that is not in good standing, they shall be required to name a replacement Subcontractor at no additional cost to the Region or shall be deemed not considered for award.
If the Vendor has ongoing Contract(s) with the Region, the Vendor must complete the Contract(s) and score a Satisfactory Rating. Anything less than Satisfactory shall result in the Vendor adding further Suspension time to the current Suspension duration.
Should the Vendor complete the Contract(s) and receive a Satisfactory Rating prior to the completion of the Suspension duration, the Vendor must complete its full Suspension duration.
If at the end of the Suspension duration the Vendor has yet to complete the Contract(s), an Interim Evaluation(s) shall be completed. If the Interim Evaluation(s) are Satisfactory, the Vendor shall move immediately into Probation Status. If it is anything less than Satisfactory, the Vendor shall stay on Suspension until Substantial Performance is achieved and the Final Evaluation(s) completed.
The Final Evaluation(s) shall determine whether the Vendor moves into Probation or another Suspension period.
Procurement shall ensure submissions from those Vendors which are no longer eligible to bid on Contracts due to their Ratings will have their submissions disqualified.
In cases where a Vendor’s Interim Evaluations are continuously not Satisfactory and the Vendor has failed to make the requested improvements, the Region reserves the right to put the Vendor on Probation until the Final Evaluation is complete, subsequently evaluated, and applicable Rating applied.
A Vendor or its representative may appeal the Final Evaluation and Rating by emailing an appeal, in writing, to Vendor Performance to the attention of the Director, Procurement, within 21 Calendar Days of receipt of the Final Evaluation.
Appeals submitted after 21 Calendar Days shall not be accepted and Vendors shall be notified of this upon submission of the appeal.
A Vendor undertaking an appeal of an assigned evaluation rating shall note that it will retain the status rating assigned to it as a result of the evaluation for the entire duration of the appeal process.
An appeal must contain:
- The Document (contract) number
- The project number
- The contract name
- The specific issues and items the Vendor disagrees with along with reasons in support of the appeal
- Any evidence the Vendor relies on or believes is relevant to the Final Evaluation and Rating, and
- Preference for an in-person meeting or paper review.
Upon receipt of an appeal, the Region shall acknowledge receipt and shall review the matter.
A committee shall be struck to perform the review and shall be comprised of the Director of Procurement or designate, the Project Lead’s Director or designate and any other individuals the Region may deem necessary such as staff from technical services, consultants, etc.
The Committee shall not include individuals that produced or were involved in the initial Final Evaluation and Rating. The Committee shall review the Vendor’s concerns and gather information from those involved in the performance of the Contract. The Committee shall conduct its review in accordance with the preference identified by the Vendor. Should the Committee’s decision be favourable to the Vendor based upon the documentary evidence submitted, the committee shall dispense with the need for an in-person meeting.
Upon review of the information, the committee shall make its decision to either confirm or vary the Final Evaluation and Rating. The decision shall contain the Committee’s reasons. The decision of the Committee shall be considered final.
The Director of Procurement or designate shall advise the Vendor of the decision in writing and copy the Project Lead. If an adjustment has been made, a revised Final Evaluation shall be provided with the decision and project and Procurement files shall be updated accordingly.
The Region reserves the right to place a Vendor on Suspension from bidding on any or all Regional Contracts while there is Litigation(s) in progress between the Region and the Vendor.
When the Region decides to exercise this right, the Vendor shall be notified in writing that they are suspended from bidding on Region Contracts as a Vendor or Sub-Contractor until further notice.
Not all Litigations shall result in Suspension: the decision to suspend or not suspend a Vendor due to Litigations is at the sole and absolute discretion of the Region.
Once the Suspension due to Litigation is removed, the Contractor shall return to Satisfactory Status if the Rating obtained on the Contract resulting in Litigation was Satisfactory, otherwise they shall complete the Suspension or Probation period as outlined within this procedure.
All Interim Evaluation(s) and the Final Evaluation are to be kept in the project file for each Contract. A copy of the Final Evaluation and any unsatisfactory Interim Evaluation(s) are to be sent to Procurement.
Final Evaluations stay on a vendor's record for a period of 5 years, after which they cannot be considered when determining appropriate Suspension duration.