Steeles Avenue noise wall replacement

Steeles Avenue from Hartford Trail to McMurchy Avenue South

Background

The Region of Peel is in the design stage of Private Noise Wall Conversion Program for your area along Steeles Avenue between Hartford Trail and McMurchy Avenue South.

Under the Program, there is no cost to you for this noise wall replacement and its future maintenance, as after conversion, these noise walls will become the Region’s responsibility.

m

Wooden (cedar) or composite concrete noise walls

The existing noise walls material is wood and can be replaced with either concrete panels or cedar wood. For either material, noise reduction properties and wall height will remain similar to the existing wall. The impact on the number of trees required to be cut down for either of the material options is 5 to 8 trees.

Examples of wood and concrete noise reduction walls:

Precast concrete sound wall – Dixie Road (from Clark Boulevard to Birchbank Road), Brampton

Precast concrete sound wall – Finch Avenue West (from Darcel Avenue to Highway 427), Mississauga

Wood noise wall – Erin Mills (South of Dundas Street West), Mississauga

Wood noise wall – Dundas Street West, at Erin Mills, Mississauga

See the material comparison chart for more information.

We need your input

Public consultation is important to the success of this project. We invite you to engage with us, discuss your concerns, and provide your feedback on the alternatives (concrete vs. wood) of the replacement noise walls material.

Please provide your feedback by Tuesday, March, 16, 2021 by email or by phone at the contacts listed below. Due to the current COVID-19 Provincial restrictions, a public consultation session cannot be held. The project team will review and consider the feedback received in selecting the noise wall replacement material. Results will be posted here once available.

Feedback Results

The following is the summary of the results received from the participants that provided feedback for the Noise Walls material preference along Steeles Avenue Noise Wall between Hartford Trail and McMurchy Avenue South.

Following is the statistics for the responses received:

Steeles Avenue (@ Hartford Trail & McMurchy Avenue S.)
Participated 67%
Wood 0%
Concrete 67%

The response rate was 67%.

Based on the feedback results, the majority of the participants prefer Concrete Noise Walls.

For any questions about the survey results or the project please contact:

Asad Rauf
Project Manager
905-791-7800 ext. 7814

Mike Neumann, P.Eng.
Consultant Project Manager, Planmac Engineering Inc.
416-626-5300 ext. 204

Councillor Martin Medeiros has also been consulted on this project. Should you have any questions or comments for him. please contact him by phone or email.

Councillor Martin Medeiros
Regional Councillor Wards 3 and 4
2 Wellington Street West,
Brampton ON, L6Y 4R2
Tel: 905-874-2634