Project 24-1310 F – December 12, 2025 update Caravelle Drive
Streets affected: Caravelle Drive
Project update
Peel Region has been replacing the watermain along Caravelle Drive. This work is required to keep providing you with high-quality water.
At this time, we have:
- Replaced the watermain,
- Connected properties to the new watermain,
- Temporarily repaired driveways, road, curbs, sidewalk and sod (grass) affected by construction.
The remaining work has been put on hold due to the weather. We’ll shut down for the winter and clean up on December 21, 2025. We will leave the construction site in a safe condition for the rest of the winter.
Schedule for remaining repair work
We expect to start again in April 2026 to complete the following:
- Complete repairing driveways, road, curbs, sidewalk and sod (grass) affected by our construction. This includes replacing the temporary asphalt on driveways, curbs, sidewalks, and roads to complete final restoration.
We plan to finish in Spring 2026. More details about restoration will be shared in a follow-up notice.
Settlement of the ground
It is normal for repaired areas to settle. Let us know if you notice large potholes forming where the driveway, street, or lawn was repaired and we’ll ensure these are fixed.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide safe drinking water to support a thriving community for life.
If you have any questions, contact us.
Water Linear Engineering
Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409