Project 23-2272 - October 1, 2026 update
Streets affected: Countryside Drive between Clarkway Drive and 700m East
Construction work in your area
Peel Region will be installing new watermains and sanitary sewers along Countryside Drive, as shown on the attached map. Watermains are underground pipes that bring tap water from our water treatment facility to your neighbourhood. As our population grows, we need to build larger watermains to provide you with high-quality water. Sanitary sewers are underground pipes that carry wastewater from your home or business to a water resource recovery facility. Wastewater is created when water goes down a drain or toilet. As our population grows, we need to build larger sewers to provide you with high-quality wastewater services.
Construction schedule
In coordination with the City of Brampton’s active road widening project, Peel Region’s construction is planned to start October 12, 2026, and finish in spring 2027. These dates may change due to weather and other unexpected events. Following completion of works, the City of Brampton’s road widening project will proceed with works in this location.
Contractor working hours
The work will be completed by Ward & Burke and supported by Arcadis as the Consultant, both under contract to Peel Region. Working hours are from 7 a.m. to 7 p.m., Monday to Friday. However, there will be periods in which the Contractor will be working outside of normal working hours (i.e. working on weekends and overnight between 7 p.m. and 7 a.m.) to reduce the impact of our works on traffic congestion and to expedite the work schedule. We apologize in advance for any inconvenience caused by this work.
Traffic and parking
We will need to temporarily close roads or reduce traffic to a single lane. If this is needed, we’ll place signs with directions.
Interrupting your water supply
We may need to temporarily shut off your water.
For residents:
- If we need to shut off your water for several hours, our goal is to let you know 48 hours (2 days) in advance. Sometimes, we must reduce this notice to 24 hours.
- If we need to shut off your water for a short time (less than one hour), we’ll knock on your door.
For businesses:
- If your business needs a continuous water supply and you have not already completed a water needs survey, please let us know when and how your business uses water. If we need to shut off your water due to an emergency, we’ll knock on your door and do everything we can to fix the problem quickly.
Construction safety
Construction zones require extra caution to keep everyone safe. Be aware of your surroundings when driving, walking, or biking near the construction area. Watch for construction crews and other road users, slow down, and consider other routes. Visit work zone safety for more information.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide safe drinking water and reliable wastewater services to support a thriving community for life.
If you have any questions, please contact us.
Water Linear Engineering & Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Peel Region