Project 23-1310 H – May 4, 2026 update
Streets affected: 7500 Goreway Drive, Mississauga
Notice of restoration
Peel Region will be repairing curbs, sidewalks, and sod (grass), following the replacement of the sanitary sewer at 7500 Goreway Dr.
Restoration schedule
Restoration work will start in the month of May at 7500 Goreway Drive. We plan to complete all work by end of May, 2026, weather permitting.
Restoration will begin by fixing curbs and sidewalks and sod replacement. This will take approximately 2 weeks.
Please note that repairs may be delayed due to contractor availability or weather conditions.
For example:
- Most sod farms are located north of Peel. They usually have sod available starting in late May. We’ll replace the sod on your property once it is available.
- In summer, we may need to postpone sod replacement due to hot, dry weather.
- We replace sod only until the middle of November, weather permitting, to let the sod grow roots. If we do not repair your lawn by the middle of November, we’ll replace the sod the following spring.

Contractor working hours
The work will be completed by VIC’s Group Inc. under contract to Peel Region. Working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with local municipal bylaws and help shorten the amount of time construction is in your neighborhood.
Traffic and parking
We may need to temporarily close roads or reduce traffic to a single lane. If this is needed, we will place signs giving directions. On-street parking will be reduced when we are working on your street.
Construction safety
Construction zones require extra caution to keep everyone safe. Be aware of your surroundings when driving, walking, or biking near the construction area. Watch for construction crews and other road users, slow down, and consider other routes. Visit work zone safety for more information.
In-ground sprinkler systems
If the area in front of your home was affected by construction, in-ground sprinkler lines may be impacted during the upcoming restoration work. We strongly recommend moving any sprinkler lines in the municipal right-of-way or next to the sidewalk. The municipal right-of-way includes the street and the municipal-owned land between the street and the water service box, a small, round, metal valve located outside on the property line between your home or business and the road.
If you cannot move these sprinkler lines, send us your irrigation map or flag each sprinkler head within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.
Replacing grassy areas
The contractor will replace any damaged sod on the boulevard or your front lawn and will take care of it for 30 days. You can help the sod stay healthy by watering it. A longer watering works better than watering more frequently for a shorter time. Early morning watering allows more water to soak in.
Warranty on construction repairs
All work is warrantied for two years from the completion date.
It is normal for repaired areas to settle. Let us know if you notice large potholes forming where the driveway, street, or lawn was repaired, and we’ll ensure these are fixed before the warranty period ends. Once the warranty period is over, Peel is no longer responsible for fixing potholes or dead sod in these locations.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide reliable wastewater services to support a thriving community for life.
Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Peel Region
Phone: 905-791-7800 ext. 4409