Peel Region will be working in your area to replace the sanitary sewer(s) along Cathcart Crescent, as shown on the attached map. Sanitary sewers are underground pipes that carry wastewater from your home to a water resource recovery facility. Wastewater is created when water goes down the drain or is flushed down the toilet. As pipes age and our population grows, we need to replace older sewers to keep providing you with high quality wastewater services.
Construction schedule
Construction is planned to begin fall 2024 and be completed in by the end of 2024. These timelines are estimates, as weather and other unexpected events may impact our timelines.
All work is under warranty for two years from the completion date.
Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices.
Contractor and working hours
The work will be completed by Nabolsy Contracting Inc. and supported by the consultant, Ainley Group, both under contract to Peel Region. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighbourhood to be under construction for a longer period of time.
Traffic and parking
We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.
Areas impacted by construction
Installing sanitary sewers usually requires digging a trench within the municipal right-of-way, which includes the street and the land owned by the municipality between the water service box and the street. (The water service box is a small, round, metal valve located outside, on the property line between your home and the road.) Depending on the location of the sanitary sewer, this trench might cause temporary damage to roads, curbs, sidewalks, boulevards, lawns, and the bottom of driveways within the municipal right-of-way.
In addition, depending on its condition, Peel Region may also repair or replace the municipal portion of the wastewater service pipe, the smaller underground pipe running from your home to the Regional sanitary sewer system. This may require digging up either the lawn or driveway above this section of pipe and disturbing an area at least two square meters.
We therefore recommend that you delay any driveway paving or major landscaping projects until this construction work is completed.
Any damage caused by Peel Region’s construction will be repaired.
In-ground sprinkler systems
As the front lawn may be affected by this construction work, if you have an in-ground sprinkler system we strongly recommend moving any sprinkler lines that are located in the municipal right-of-way or next to the sidewalk. If you can’t relocate these sprinkler lines, please send us a map created by your irrigation contractor or flag each sprinkler head that is located within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.
Tree trimming
If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand.
If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. The contractor will contact you before any pruning of private trees occurs. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.
Repairing areas impacted by construction
We will start repairing the road, curb, sidewalk, driveways, and lawns once the new sanitary sewer is buried and work has been completed on all wastewater service pipes on your street.
Repairs may be delayed due to contractor availability or certain seasonal weather conditions.
For example:
- Paving cannot take place when the ground is saturated with water, or the temperature is below 3°C.
- Asphalt is not available in large volumes during the winter. Asphalt usually becomes available around mid-May.
- Most sod farms are located north of Peel. They usually have sod available beginning in late May. We will replace the sod on your property once it is available. We replace sod only until the middle of November, weather permitting, to let the sod grow roots. If we do not repair your lawn by the middle of November, we’ll replace the sod the following spring.
Repairing grassy areas
The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.
Repairing driveways
- Asphalt driveways: If we need to cut a section of your driveway, the driveway will be repaired by paving a stripe over the disturbed area, resulting in minimal seams in the final driveway. Peel Region cannot replace your entire driveway. If you would like to have the rest of your driveway paved, there may be an opportunity to work with the contractor during restoration works. The contractor may be able to share contact information for the company hired to do the paving repairs. Please remember this is your option. If you decide to have your entire driveway repaved, this extra paving work is your responsibility and outside the jurisdiction of Peel Region.
- Interlock or concrete driveways: If we damaged a portion of your driveway, our contractor will reinstate the damaged portion of the driveway.
Driveway access
It may be necessary to block your driveway for a short time when crews are digging the trench for the sanitary sewer, working on your wastewater service pipe, or completing other construction activities. If so, we will knock on your door to notify you. If a trench prevents access to your driveway, the contractor will have metal road plates available to allow access if required. Whenever possible, we will work to ensure businesses can be accessed. Please contact us if you have special needs related to access.
Waste collection
If you receive waste collection from Peel Region, your garbage, recycling, and organics will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin. This helps us return empty bins to the correct address.
Vibrations
You could feel slight vibrations from the construction work.
Optional protection plans for your exterior water pipes, wastewater pipes, and in-home plumbing
Many homeowners are not aware that they are responsible for maintaining the water and wastewater pipes both inside their home and outdoors up to the property line. If one of these pipes breaks, it can cause unexpected and costly repairs. Peel Region has partnered with Service Line Warranties of Canada (SLWC) to offer homeowners optional, affordable protection from unexpected home repairs. Learn more about the protection plans at plansforpeel.ca.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/workzonesafety.
Keeping you informed
We will let you know if there are any major changes to the plans.
Information on this project can also be found on the project webpage.
Follow Peel Public Works on Twitter for project updates.
We value your feedback
After we have finished, we will invite you to provide feedback on the construction project.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality wastewater services. If you have any questions, please contact us.