Project 22-2300 A2 and 20-2300 N – July 23, 2026 update
Streets affected: Staveley Crescent, Cathedral Road and Bartley Bull Parkway
Project update
As part of the Flow | Central Brampton Program, Peel Region will be rehabilitating the sanitary lateral services along Staveley Crescent, Bartley Bull Parkway & Cathedral Rd. Sanitary sewers are underground pipes that carry wastewater from your home to a water resource recovery facility. Wastewater is created when water goes down a drain or toilet.
At this stage, we will be relining a portion of the wastewater service pipe which carries wastewater from your home to the sanitary sewer.
We will clean the sewer pipe and place a new resin (plastic) lining inside it to extend its life. This work will be completed by Nabolsy Contracting Inc. under contract to Peel Region.
We typically only line the portion of the wastewater service pipe within municipal property, as it’s your responsibility to maintain the portion on private property.
To line the wastewater service pipe, we may need to dig a hole approximately two square meters. This hole will be dug where the pipe crosses your front property line in the lawn or driveway to provide access to the pipe. This work will result in minimal impact to you.
Construction schedule
We’ll start relining wastewater service pipes on Staveley Crescent around August 17, 2026. Once this street is completed, we’ll proceed to Cathedral Road and followed by Bartley Bull Parkway. We expect it to be finished by August 24, 2026.
All work is warrantied for 2 years from the completion date.
Wastewater service interruptions
To complete this work, your wastewater service pipe will be out of service for approximately 8 hours. This interruption allows for the pipe to be repaired without digging trenches. The contractor will provide a second notice with a date and time at least 24 hours before the lining process begins.
It is important to minimize your water use during this work:
- You may continue to wash your hands but minimize your water use.
- Do not use showers, bathtubs, dishwashers, or your washing machine.
- Keep toilet flushing to a minimum.
These actions will reduce the possibility of wastewater backing up into your basement or plumbing. If you have a sump pump, please notify us at construction@peelregion.ca or tell the contractor when they arrive.
Odours
You may smell some odours while the resin inside the sewer cures. These odours will go away within a few hours. You can prevent or minimize this by pouring a bucket of water down the basement floor drain and running water in all sinks, showers, and tubs for a minute, either the evening before or day of the relining work. If this is not possible (for example, if it is currently covered by flooring), we strongly recommend making it accessible before construction begins to reduce odours.
Construction safety
Construction zones require extra caution to keep everyone safe. Be aware of your surroundings when driving, walking, or biking near the construction area. Watch for construction crews and other road users, slow down, and consider other routes. Visit work zone safety for more information.
Damages from our construction will be repaired
- If we dig up your lawn, we’ll replace the sod (grass) in the impacted area.
If we cut a section of your driveway, it will be repaired by paving a strip over the impacted area, resulting in minimal seams.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
- More information on the Flow Program can be found on the website.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide reliable wastewater services to support a thriving community for life.
If you have any questions, contact us.
Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Peel Region
Phone: 905-791-7800 ext. 4409