Project 22-2255 - March 25, 2025 update
Street affected: Queensway East
Night work notice
Peel Region has identified the need for a new gravity trunk sewer along the Queensway East, which will provide the required level of service to support growth in the City of Mississauga. The Queensway East Trunk sewer (QET) will span from Hurontario Street to Etobicoke Creek.
The City of Mississauga, under the Noise Bylaw, is allowing work to be carried out by the contractor (Geophysics GPR International Inc.) overnight. The work involves conducting a non-invasive land survey for the purpose of identifying the quality of the soil and rock. This overnight work will occur along the Queensway, from 35 m West of Hurontario St. and 35 m East of Cliff Road. A sketch of the working area is attached.
We apologize in advance for any inconvenience caused by this work.
Schedule
This overnight work is expected to take place for multiple evenings, from April 3rd 2025 to April 9th 2025 between the hours of 10PM to 5AM, Monday to Friday. Additional nights may be required due to unpredictable delays, such as poor weather conditions.
Traffic impacts
The night shift will require a temporary westbound curb lane closure on Queensway East from 35m West of Hurontario to 35m East of Cliff Road. We will have paid duty officers assisting with traffic movement at all impacted intersections
Noise
We do not anticipate significant noise or vibrations above normal daytime construction levels during these operations. Efforts will be made to reduce impacts to local residents as much as possible.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn more about how to stay safe in construction zones.
Staying informed
We will let you know if there are any major changes to the plans. Receive timely project updates right to your inbox by signing up for e-notices.
Information on this project can also be found on the project webpage.
We understand that construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world class water systems, allowing us to provide safe drinking water and reliable wastewater services to support a thriving community for life. If you have any questions, please contact us.
Wastewater Collection and Conveyance Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca
Phone: 905-791-7800, ext. 4409