Project 19-2215 – April 24, 2026 update
Streets affected: Lakeshore Road at Pine Avenue South
Project update
Peel Region will be installing a new watermain and large sanitary sewer along Lakeshore Road between Jack Darling Memorial Park and Elmwood Avenue, and a new sanitary sewer on Wesley Avenue from Park Street to Lakeshore Road West. We will also be replacing a section of watermain between Ibar Way and Shawnmarr Road. For more information on the project, visit our project webpage.
Noise and Work Schedule
An exemption has been made under the City of Mississauga Noise By-law to allow work to take place overnight between 7 p.m. to 7 a.m. to reduce the impact of our work. It will take place over two nights between May 1, 2026, and May 8, 2026.
We do not expect significant noise or vibrations above normal daytime construction levels during this time. Efforts will be made to reduce impacts to residents.
Construction Safety
Construction zones require extra caution to keep everyone safe. Be aware of your surroundings when driving, walking, or biking near the construction area. Watch for construction crews and other road users, slow down, and consider other routes. Visit work zone safety for more information.
Get the latest updates
- Sign up for e-notices.
- Follow Peel Public Works on X
- Follow Peel Region Instagram #lakeshoreproject
- Follow Peel Region on Facebook #lakeshoreproject
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide wastewater services to support a thriving community for life.
If you have any questions, contact us.