Project 18-1357 - May 8, 2026 update
Street affected: 32 Wellington Street West
Storm sewer repair
As part of the Flow | Central Brampton Program, Peel Region will be repairing the storm sewer at 32 Wellington Street West. Thank you for your cooperation while we finish this work.
Construction schedule
Construction for the storm sewer repair at 32 Wellington Street West will take place from Tuesday, May 12, 2026, until Thursday, May 14, 2026. These dates may change due to weather and other unexpected events. All work is warrantied for two years from the completion date.
Contractor working hours
The work will be completed by Machina Construction under contract to Peel Region. Working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with local municipal bylaws and help shorten the amount of time construction is in your neighborhood.
Traffic and parking
Work is taking place in front of 32 Wellington Street West. The section of road directly in front of the house will be closed, and on street parking will be reduced in the work zone. An “Automated Flagger Assistance Device” will be posted to manage vehicle flow. Drivers should slow down and follow all posted signs when approaching the area.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
- More information on the Flow Program can be found on the program webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide safe drinking water to support a thriving community for life.
If you have any questions, contact us.
Engineering Services Division
Public Works, Peel Region
Phone: 905-791-7800, ext. 4409