Project 18-1357 – December 17, 2025 update
Street affected: Queen Street West
Project update
As part of the Flow | Central Brampton Program, Peel Region has been replacing the watermain along Queen Street West. This work is required to keep providing you with high-quality water.
We’ll shut down for a winter break starting December 22, 2025, and be returning to work on January 12, 2026. We will leave the construction site in a safe condition during this time.
Schedule for remaining construction
- The majority of all underground construction work has been completed.
- We are on schedule to complete all road and bridge work over Fletcher’s Creek by mid-2026.
- More details about restoration will be shared in a future notice.
Settlement of the ground
It is normal for repaired areas to settle. Let us know if you notice large potholes forming where the driveway, street, or lawn was repaired and we’ll ensure these are fixed.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
- More information on the Flow Program can be found on the program webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us to provide safe drinking water to support a thriving community for life.
If you have any questions, contact us.