Project 17-2280 - October 25, 2022 update
Streets affected: Sanitary Sewer along Harvestview Avenue and Sant Farm Drive
The Region of Peel has been working in your neighborhood to install a new sanitary sewer. This work is required to maintain and improve existing wastewater services.
At this stage in the project, we need a new sanitary sewer along Harvestview Avenue and Sant Farm Drive.
Project details
The work will be completed by Earth Boring Co. Limited and supported by Chisholm Fleming and Associates Consultants, both under contract to the Region of Peel. The pipe will be installed underground using open cut trenching methodology.
Construction Schedule
This work is scheduled to begin on October 31st, 2022. Below is the tentative schedule and sequence of works. Please note that these days are subject to change due to unforeseen circumstances:
- Sant Farm Drive from November 1st to November 18th, 2022
- Harvestview Avenue from November 21st to December 6th, 2022
Mainline Sanitary Sewer works will be completed this year. We will be returning in Spring 2023 to complete the sanitary services connections as well as make all necessary repairs to the road, boulevard, curb or sidewalk. All work is under warranty for two years from the completion date.
Working hours
Our contractor's normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality's bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighbourhood to be under construction for a longer period of time.
Traffic impacts
We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.
- Sant Farm Drive will require a single lane closure of the northbound lane between Queensgate Boulevard and Harvestview Avenue. Southbound lane will remain open to one-way local traffic only. Northbound traffic will be re-directed through a detour route which will be clearly marked with road signs.
- Harvestview Avenue will require a single lane closure of the eastbound lane between Sant Farm Drive and Esposito Drive. Westbound lane will remain open to one-way local traffic only.
Those residents who live on Sant Farm Drive and Harvestview Avenue where we are actively working access to homes will be provided.
Safety during construction
Construction zones require extra caution to keep everyone safe - pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn more about how to stay safe in construction zones.
Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices.
Keeping you informed
We will let you know if there are any major changes to the plans.
Information on this project can also be found on the project webpage.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality wastewater services. If you have any questions, please contact us.
Wastewater Collection and Conveyance,
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409