Project 17-2280 - June 1, 2026 update
Streets affected: Harvestview Avenue and Sant Farm Drive
Project update
Peel Region has recently installed various sanitary sewers within the Albion Vaughan Road, Harvestview Ave, Old King Road, Nunnville Road, Queensgate Boulevard and Sant Farm Drive.
As part of one of the final phases of the project, re-direction of sanitary sewer flows will take place at the following locations:
- 10 Harvestview Ave including the abandonment and demolition of Harvestview Sewage Pumping Station
- Sant Farm Drive & Riverwood Terrace/Allan Drive
- Sant Farm Drive & Riverwood Terrace North
Schedule
This work is expected to take place between June 4, 2026, until July 3, 2026. Additional days may be required due to weather and other unexpected events.
Traffic impacts
This work will require temporary lane closures. We will place signs giving directions. The working hours are from 7 a.m. to 7 p.m.
Noise
We do not expect significant noise or vibrations above normal daytime construction levels during this time. Efforts will be made to reduce impacts to local residents.
Construction safety
Construction zones require extra caution to keep everyone safe. Be aware of your surroundings when driving, walking, or biking near the construction area. Watch for construction crews and other road users, slow down, and consider other routes. Learn more about how to stay safe in construction zones.
Get the latest project updates
- Sign up for e-notices.
- Project information can be found on the project webpage.
We understand construction can be disruptive, and we appreciate your patience as we work to improve our community’s infrastructure. This work both maintains and improves Peel’s world-class water systems, allowing us reliable wastewater services to support a thriving community for life.