Sanitary sewer improvement

Nunnville Road. Project 17-2280

The Region of Peel has been working in your area to install new sanitary sewers along Albion Vaughan Road, Nunnville Road, Old King Road, Queensgate Boulevard, Harvestview Avenue, Sant Farm Drive, and Riverwood Terrace. Wastewater is created when water goes down the drain or is flushed down the toilet. As our population grows, we need to build new sewers to keep providing high quality wastewater services.

At this stage in the project, we will be starting to tunnel a new sewer along Nunnville Road. Construction activities will take place within the two tunnel access points that were previously dug along Nunnville Road.

Construction schedule

Below is the tentative schedule for construction work along Nunnville Road:

These timelines are estimates, as weather and other unexpected events may impact our timelines.

Construction and repair work completed as part of this project is under warranty for two years from the completion date.

Contractor and working hours

The work will be completed by Earth Boring Co. Limited and supported by Chisholm Fleming and Associates Consultants, both under contract to the Region of Peel. Our contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Saturday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighbourhood to be under construction for a longer period of time.

Traffic impacts

Nunnville Road will continue to be reduced to a single shared lane at the tunnel access points. Where a single lane is shared with oncoming traffic, please be sure to yield to oncoming traffic as stated by the road signs.

On-street parking will be reduced during construction when we are actively working on your street.

Safety during construction

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn more about how to stay safe in construction zones.

Keeping you informed

We will let you know if there are any major changes to the plans.

Receive timely project updates right to your inbox by signing up for e-notices. Information on this project can also be found on the project webpage.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality wastewater services. If you have any questions, please contact us.

Wastewater Collection and Conveyance,
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409