Queen Street improvements in Bolton
Elizabeth Street to Hickman Street. Projects 09-4830, 10-4910 and 17-4635
Project updates
- September 2019 Project Update- Sidewalk Improvements (PDF)
- We have finished the work. The project is under warranty until August 31, 2020.
- Street lighting improvements taking place in January and February, 2018.
- Queen Street Improvements Downtown Bolton (PDF)
- Top Asphalt Paving October 25 to 26, 2017 (PDF)
- October 11, 2017 (PDF)
- Queen Street Improvements Starting May 29, 2017 (PDF)
- Public Notice of Open House
- Open House Display Boards (PDF)
- Water and Sewer Works Starting March 6, 2017 (PDF)
What we are doing
- Replacing all decorative streetlight poles between Hickman Street and Willow Street.
- Installing cobra style streetlight poles on top of the retaining wall west of Queen Street, south of King Street.
- Replacing banner poles with decorative streetlight poles between Willow Street and Norton Boulevard.
- Rehabilitation of Humber River Bridge
- Bridge deck repairs and waterproofing
- New decorative railings
- Removal of the sidewalk on the west side
- Widening of the sidewalk on the east side
- Traffic Signals and Street Lighting
- Removal of signalized intersection at Mill Street
- New signalized intersection at Hickman Street
- New signalized pedestrian crossing at Sterne Street
- Street lighting enhancement between King Street and Elizabeth Street
- Rehabilitation of culvert under Queen Street South
- Rehabilitation of retaining walls on the west side of Queen Street South
- Sidewalk improvements
- For further details, please see the scope of work drawings
- Asphalt paving onQueen Street North from Sterne Street to Hickman Street (PDF)
When
- Start: May 29, 2017
- Finish: October 2017, weather permitting
Who you can call
Contractor Personnel - Marbridge Construction Ltd. Under contract to the Region of Peel. |
||
Contact | Responsibilities | Telephone |
---|---|---|
Walter Marsetti | Site Supervisor | 416-881-8202 (24 hour emergency contact) |
Tod Markelj | Project Manager | 416-881-8201 |
Consultant Personnel - GHD | ||
Erik Rimas-Ribikauskas | Contract Administrator | 416-317-1913 |
Michael Shallhorn | Project Manager | 905-429-5023 |
Region of Peel Personnel | ||
Olek Garbos | Project Manager | 905-791-7800 Ext. 7827 |
Mirgjen Arkaxhiu | Construction Inspector | 905-791-7800 Ext. 3246 |
Rebecca Caughey | Traffic Signals | 905-791-7800 Ext. 7851 |
Denise Dang | Traffic Operations | 905-791-7800 Ext. 7853 |
Working hours
- Our contractor’s normal working hours are from 7a.m. to 7p.m.
- We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete
Traffic control
- Queen Street North will be reduced to one lane in each direction for the duration of the project.
- Lane closures for all other work will be done in non-peak hours.
- Ontario Provincial Police will be present during lane closures at all intersections to direct traffic safely.
- Emergency access will be maintained at all times.
- Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.
- For more information see the Proposed Construction Staging and Traffic Detour drawings.
Driveway access
- If we need to block your driveway you will be contacted for alternate access.
- We will make sure businesses have access at all times.
- Please call the Project Manager if you have special needs related to access or business hours
Project updates
- The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
- We are committed to ensuring minimum disruption to your homes and businesses.
- Please call the project manager or inspector if you have any special needs.