Project 12-4085
Reconstruction of The Gore Road
Streets affected: Patterson Side Road to 100m North Finnerty Sideroad
Update notice: The Gore Road closure, local traffic only; August 26, 2024 to September 11, 2024.
Further to our Resident Notices dated September 11, 2023, November 15, 2023, and August 14, 2024, Peel Region is committed to keeping you informed of the progress of this project and any changes to the project schedule. This project has been progressing well; however, it is necessary to extend the current road closure installed on August 26, 2024, to September 11, 2024, between Patterson Side Road and Finnerty Side Road to continue safely installing the remaining large pipe culvert; please refer below for an established detour map.
The works completed to date includes driveway culvert replacement, removals, implementation of retaining walls, eco-passage culvert and road re-construction.
Construction schedule:
The reconstruction of The Gore Road is anticipated to be completed by the end of 2024 with some finishing works in early 2025. The remaining works include culvert installation, road reconstruction, Hot Mix Asphalt paving, retaining wall installation, pavement markings, and landscaping.
Traffic control
The Gore Road will be closed to through traffic. Local access will be permitted from either ends of the road closure limits. Emergency services if required will be permitted.
Waste collection and mail delivery
We do not anticipate any changes to your garbage and recycling schedule. Please mark your house number on your containers or bins to help with identification. Should there be any changes to mail delivery, you will be notified in advance.
Who can you call?
Pacific Paving Ltd |
||
---|---|---|
Contact Person | Responsibilities | Telephone Number |
Jasleen Matharu | Project Manager | 416-200-4074 |
Mike Wright | SiteSuperintendent | 416-317-3103 |
Peel Region |
Contact Person | Responsibilities | Telephone Number |
Randy Chawb-Naraine | Project Manager | 905-791-7800 ext. 7962 |
Sajmir Zesllari | Construction Inspector | 905-872-2230 |
R.J Burnside & Associates Limited |
Contact Person | Responsibilities | Telephone Number |
Gustavo Izquierdo | Contract Administrator | 905-821-5927 |
David Argue | Project Manager | 905-821-5895 |
Project Updates
Peel Region is committed to keeping you informed and ensuring that the works are carried out with minimum disruption to your homes and businesses. If there are any substantial changes in the project scope or schedule, you will be provided with project updates. We also encourage you to notify the appropriate contact person to advise them of any problems or particular needs. We thank you in advance for your cooperation.
Thank you,
Randy Chawb-Naraine
P.Eng. Project Manager
Transportation Division, Roads – Design and Construction