Watermain replacement in Malton
Assignment B, City of Mississauga, Project 19-1310 B
What are we doing?
- Reinstating driveways, sod, and curb following the replacement of the watermain and services along Laddie Crescent.
- To complete restoration following upgrade of the water distribution system.
When?
- We expect to start work on or about October 20th, 2021.
- The restoration works should be completed by November 2nd, 2021.
Who can you call?
Region of Peel | ||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Mark Ferreira | Project Manager | 905-791-7800, ext. 5119 |
George Da Re | Inspector | 905-791-7800, ext. 3246 |
Timbel Limited Timbel Limited will do the work, under contract to the Region of Peel | ||
Bruno Bellissimo | Project Manager | 416-706-7883 |
Traffic and Parking Control
- We may need to reduce traffic to a single lane during construction.
- If we have to reroute traffic, we will place signs giving directions.
Driveway Access
- Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed.
- During the construction of the concrete curb crossing driveways, homeowners will be required to park on the roadway on the opposite side of the construction works.
- Please call the Project Manager if you have special needs related to access or business hours.
Replacing and Taking Care of Your Sod
- The contractor will take care of any sod we replace for 30 days.
- You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
- We will replace your sod as soon as we can, but there may be a short delay.
- It is very common for the work area to settle a bit following construction. If you notice any settlement, please let the project manager or inspector know and we will ensure the contractor fixes it.
Repairing Your Driveway
- If we have cut your driveway, we will repair the asphalt in the disturbed area from edge to edge across the driveway. Unfortunately the Region cannot completely replace your driveway.
- We will repair your driveway as soon as we can, but there may be a short delay.
- If you would like to have the rest of your driveway paved at this time, please either contact the contractor named on the front of this letter. The contractor will then refer you to the subcontractor being used for this project. Please do not accept direct solicitation from any contractor telling you that they have been retained by the Region. Please remember this is your option. If you choose to do nothing, we will repair all areas damaged by our construction; however, we are unable to completely replace your driveway.
Project Updates
- The Region of Peel will always let you know if there are any major changes to the plans.
- We will try to disturb you as little as possible.
- Please call the project manager or inspector if you have any problems or special needs.
Construction statement regarding COVID-19
Construction is an essential service. We’re keeping employees, contractors and the community safe by complying with provincial regulations, physical distancing, using personal protective equipment, and adjusting work schedules and shifts.