Watermain installation

Kennedy Road: Williams Parkway to Vodden Street East. Project 18-1155

What we are doing

Why

  1. We will mark the location of gas, hydro, cable, etc. on roads, driveways and lawns.
  2. We may drill boreholes to determine ground conditions.
  3. We may survey your street.
  4. We will take pictures to help us make sure we restore the area to its former condition.

When

Who you can call

Region of Peel
Contact Responsibilities Phone Number
David Abreu Project Manager 416-274-9164
Mark Ferreira Inspector 905-452-2926
EXP Consulting
Project Design and Contract Administration
Dudistir Gookul Contract Administrator 647-295-3281
Yousri Ibrahim Construction Inspector 416-587-1238
Moretti Construction
Moretti Construction will do the work, under contract to the Region of Peel
Valeria Cuervo Project Manager 647-571-7080
Tom Tauriello Supervisor 416-990-7373

Working hours

Traffic and parking control

Driveway access

Irrigation or sprinkler systems

Trimming trees

Interrupting your water supply

Waste collection

Vibrations

Replacing and taking care of your sod

Repairing your driveway

Repairing the roads, curbs, and sidewalks

Project updates

How did we do